Schedule of Proposed Actions (SOPA)
07/01/2021 to 09/30/2021
Chequamegon / Nicolet National Forest

This report contains the best available information at the time of publication. Questions may be directed to the Project Contact.
Report Contents (click to jump to a section) :
Projects Occurring Nationwide
R9 - Eastern Region, Chequamegon / Nicolet National Forest, Forestwide (excluding Projects occurring in more than one Forest)
R9 - Eastern Region, Chequamegon / Nicolet National Forest, Occurring in more than one District (excluding Forestwide)
R9 - Eastern Region, Chequamegon / Nicolet National Forest,  Eagle River-Florence Ranger District (excluding Projects occurring in more than one District)
R9 - Eastern Region, Chequamegon / Nicolet National Forest,  Great Divide Ranger District (excluding Projects occurring in more than one District)
R9 - Eastern Region, Chequamegon / Nicolet National Forest,  Lakewood-Laona Ranger District (excluding Projects occurring in more than one District)
R9 - Eastern Region, Chequamegon / Nicolet National Forest,  Medford-Park Falls Ranger District (excluding Projects occurring in more than one District)
R9 - Eastern Region, Chequamegon / Nicolet National Forest,  Northern Great Lakes Visitor Center (excluding Projects occurring in more than one District)
R9 - Eastern Region, Chequamegon / Nicolet National Forest,  Washburn Ranger District (excluding Projects occurring in more than one District)

Projects Occurring Nationwide  

 
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Locatable Mining Rule - 36 CFR 228, subpart A.
EIS

           *UPDATED*
- Regulations, Directives, Orders  On Hold  N/A  N/A Sarah Shoemaker
907-586-7886
sarahshoemaker@fs.fed.us 
Description: The U.S. Department of Agriculture proposes revisions to its regulations at 36 CFR 228, Subpart A governing locatable minerals operations on National Forest System lands.A draft EIS & proposed rule should be available for review/comment in late 2020
Web Link:  http://www.fs.usda.gov/project/?project=57214
Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. LEGAL - Not Applicable. These regulations apply to all NFS lands open to mineral entry under the US mining laws. More Information is available at: https://www.fs.usda.gov/science-technology/geology/minerals/locatable-minerals/current-revisions.
Back To Top

Chequamegon / Nicolet National Forest, Forestwide (excluding Projects occurring in more than one Forest)  

R9 - Eastern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
2021 Special Use Permit Project
CE

           *NEW LISTING*
- Special use management  Developing Proposal
Est. Scoping Start 06/2021 
Expected:07/2021  08/2021 Kelly Scarbrough
715-362-1314
Kelly.Scarbrough@usda.gov 
Description: Authorize requests for 14 special use permits. 8 road use permits (5 new and 3 renewal), 1 well permit renewal, 1 storage shed permit renewal,1 sign renewal, 1 dock renewal, and 2 recreation event permits(1 new and 1 renewal)
Web Link:  http://www.fs.usda.gov/project/?project=60041
Location: UNIT - Chequamegon / Nicolet National Forest All Units. STATE - Wisconsin. COUNTY - Ashland, Bayfield, Florence, Forest, Langlade, Oconto, Price, Sawyer, Taylor. LEGAL - Not Applicable. Various locations across the National Forest.
Forestwide Oak Wilt Disease Management
EA

           *UPDATED*
- Vegetation management (other than forest products)  In Progress:
Scoping Start 03/24/2020
Est. Comment Period Public Notice 07/2021 
Expected:09/2021
 
10/2021 Nicole Molitor
715-634-4821 x2327
nicole.g.molitor@usda.gov 
Description: We propose to allow prompt treatment (using a variety of tools) of oak wilt infection centers wherever found as soon as possible following discovery to slow and control the spread of oak wilt on Forest lands.
Web Link:  http://www.fs.usda.gov/project/?project=57903
Location: UNIT - Chequamegon / Nicolet National Forest All Units. STATE - Wisconsin. COUNTY - Ashland, Bayfield, Florence, Forest, Langlade, Oconto, Oneida, Price, Sawyer, Taylor, Vilas. LEGAL - Not Applicable. Forestwide.
Recreation Facility Strategy
CE
- Recreation management
- Facility management 
In Progress:
Scoping Start 10/30/2017 
Expected:07/2021
 
07/2021 Timothy Vetter
715-362-1373
timothy.vetter@usda.gov 
Description: The Recreation Facility Strategy prioritizes developed recreation site investments. Proposal has varying actions at 82 sites (from increased amenities to decreased maintenance) and removal of amenities at 22 sites to convert them to general forest.
Web Link:  http://www.fs.usda.gov/project/?project=55748
Location: UNIT - Chequamegon / Nicolet National Forest All Units. STATE - Wisconsin. COUNTY - Ashland, Bayfield, Florence, Forest, Langlade, Oconto, Oneida, Price, Sawyer, Taylor, Vilas. LEGAL - Not Applicable. Developed recreation sites on all ranger districts across the Chequamegon-Nicolet National Forest.
Back To Top

Chequamegon / Nicolet National Forest, Occurring in more than one District (excluding Forestwide)  

R9 - Eastern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
2021 WPS Nicolet
CE

           *NEW LISTING*
- Special use management  In Progress:
Scoping Start 06/24/2021 
Expected:08/2021
 
08/2021 Joan Stanfield-Smith
715-362-1300
jstanfieldsmith@fs.fed.us 
Description: Project is located along roads on the Nicolet side of the forest. WPS is maintaining and upgrading their lines.
Web Link:  http://www.fs.usda.gov/project/?project=60115
Location: UNIT - Eagle River-Florence Ranger District, Lakewood-Laona Ranger District. STATE - Wisconsin. COUNTY - Forest, Oconto, Oneida. LEGAL - Not Applicable. Nicolet side of the forest.
2021 Watershed Improvement Project
CE

           *UPDATED*
- Wildlife, Fish, Rare plants
- Watershed management 
Completed  Actual: 04/21/2021  05/2021 Jennifer Maziasz
715-373-2667
jennifer.maziasz@usda.gov 
Description: Watershed improvement projects: culvert replacements to reduce erosion and improve fish/aquatic passage, installation of a hardened trail crossing, road reconstruction with improved drainage, and replacement or rehab of road and trail bridges.
Web Link:  http://www.fs.usda.gov/project/?project=59261
Location: UNIT - Eagle River-Florence Ranger District, Lakewood-Laona Ranger District, Medford-Park Falls Ranger District, Great Divide Ranger District. STATE - Wisconsin. COUNTY - Ashland, Bayfield, Forest, Oconto, Price, Sawyer, Vilas. LEGAL - Approximately 30 locations across the seven counties. See website for project descriptions, exact locations, and map. Watershed improvement projects are scattered across the four districts.
Krawze Land Exchange
EA

           *NEW LISTING*
- Land acquisition  Developing Proposal
Est. Scoping Start 08/2021 
Expected:03/2022  03/2022 Mary Scheuerman
715-362-1331
mary.scheuerman@usda.gov 
Description: Exchanging land on the east side of the forest. Lakewood-Laona Ranger District in Forest County would be exchanging land for land in Eagle River-Florence Ranger District.
Web Link:  http://www.fs.usda.gov/project/?project=59900
Location: UNIT - Eagle River-Florence Ranger District, Lakewood-Laona Ranger District. STATE - Wisconsin. COUNTY - Florence, Forest. LEGAL - Not Applicable. East side of the forest in Forest and Florence Counties.
Nicolet Gravel Pit Expansion
EA

           *NEW LISTING*
- Minerals and Geology  Developing Proposal
Est. Scoping Start 08/2021 
Expected:01/2022  05/2022 Greg Knight
715-748-4875 ext 7484826
greg.knight3@usda.gov 
Description: This project would expand 16 existing gravel pits on the east side of the forest.
Web Link:  http://www.fs.usda.gov/project/?project=59901
Location: UNIT - Eagle River-Florence Ranger District, Lakewood-Laona Ranger District. STATE - Wisconsin. COUNTY - Florence, Forest, Oconto, Vilas. LEGAL - Not Applicable. East side of the forest.
North Country Trail Dispersed Campsite Development and Improvements
CE
- Recreation management  In Progress:
Scoping Start 04/12/2019 
Expected:05/2022
 
05/2022 Katherine LeMoine
715-634-4821 x2326
katherine.lemoine@usda.gov 
Description: Eight to 10 backpacker campsites would be developed or improved to provide long-distance hikers a consistent experience when they hike the North Country Trail in Wisconsin.
Web Link:  http://www.fs.usda.gov/project/?project=55297
Location: UNIT - Washburn Ranger District, Great Divide Ranger District. STATE - Wisconsin. COUNTY - Ashland, Bayfield. LEGAL - Not Applicable. Multiple sites along the North Country Trail in Great Divide and Washburn Ranger Districts.
Back To Top

Chequamegon / Nicolet National Forest,   Eagle River-Florence Ranger District (excluding Projects occurring in more than one District)

R9 - Eastern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
2021 Brule Controlled Burn CE
CE

           *UPDATED*
- Wildlife, Fish, Rare plants
- Fuels management 
In Progress:
Scoping Start 01/08/2021 
Expected:10/2021
 
10/2021 Steve Janke
715-276-6333 x4229
steve.janke@usda.gov 
Description: To maintain a wildlife opening by the Brule River and extend fire boundaries to the Brule River to act as a natural fire line instead of creating dozer dug control lines. Using the Brule River as a fire control line will better protect firefighters.
Web Link:  http://www.fs.usda.gov/project/?project=59328
Location: UNIT - Eagle River-Florence Ranger District. STATE - Wisconsin. COUNTY - Florence. LEGAL - Not Applicable. The maintenance of a large wildlife openings at the Brule River Opening (T41NR15E, Section 24 and T41NR16E Section 19). The area is a remnant farm field near the Brule River in Florence County, Wi.
Aspen-Spruce-Fir Restoration Project
EA

           *UPDATED*
- Forest products
- Vegetation management (other than forest products)
- Fuels management 
In Progress:
Scoping Start 12/17/2020
Est. Comment Period Public Notice 10/2021 
Expected:12/2021
 
01/2022 Chad Kirschbaum
715-479-2827
chad.kirschbaum@usda.gov 
Description: The Aspen-Spruce-Fir Restoration Project (ASFR) proposes to treat pockets and areas of dead, dying, diseased, and other hazard trees across the entire ERFL district. Up to 9,200 acres are proposed for active management actions.
Web Link:  http://www.fs.usda.gov/project/?project=59159
Location: UNIT - Eagle River-Florence Ranger District. STATE - Wisconsin. COUNTY - Florence, Forest, Oneida, Vilas. LEGAL - Not Applicable. Spread across the entire Eagle River-Florence Ranger District.
Back To Top

Chequamegon / Nicolet National Forest,   Great Divide Ranger District (excluding Projects occurring in more than one District)

R9 - Eastern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
ATV Trail Reroute to use Portion of Snowmobile Trail 21 from Forest Road 203 to North Scheers Road
CE

           *NEW LISTING*
- Recreation management  In Progress:
Scoping Start 06/29/2021 
Expected:07/2021
 
08/2021 Chad Jacobson
715-264-2511
chadjacobson@fs.fed.us 
Description: The Sawyer County Snowmobile ATV Alliance has submitted a proposal to allow ATVs to use a portion of Snowmobile Trail 21 from Forest Road 203 to North Scheers Road. Three gates and a culvert will need to be installed. Alliance will do maintenance.
Web Link:  http://www.fs.usda.gov/project/?project=60379
Location: UNIT - Great Divide Ranger District. STATE - Wisconsin. COUNTY - Sawyer. LEGAL - Not Applicable. Snowmobile Trail 21 from Forest Road 203 to North Scheers Road.
Forest Lodge Nature Trail Trailhead Parking Area and Traffic Circulation
CE

           *UPDATED*
- Watershed management
- Facility management 
In Progress:
Scoping Start 05/28/2021 
Expected:03/2022
 
04/2022 Debra Proctor
715-580-0412
debra.proctor@usda.gov 
Description: Improve Forest Lodge road and trail infrastructure to accommodate increased use of Forest Lodge and the Nature Trail - parking, road and trail capacity, drainage, stormwater treatment, traffic sight lines within the complex and ingress and egress.
Web Link:  http://www.fs.usda.gov/project/?project=58868
Location: UNIT - Great Divide Ranger District. STATE - Wisconsin. COUNTY - Ashland. LEGAL - Not Applicable. Forest Lodge is located about eight miles east of Cable, Wisconsin.
Forest Road 167 Reroute around Gates Lake
EA

           *NEW LISTING*
- Watershed management
- Road management 
Developing Proposal
Est. Scoping Start 07/2021 
Expected:12/2021  06/2022 Nicole Molitor
715-634-4821, x 2327
nicole.g.molitor@usda.gov 
Description: A re-route of 0.54-mile segment of Forest Road 167 is proposed. The proposed reroute will follow high ground around Gates Lake, including Forest Road W232416. It will remove a 0.16-mile road segment from Gates Lake.
Web Link:  http://www.fs.usda.gov/project/?project=60427
Location: UNIT - Great Divide Ranger District. STATE - Wisconsin. COUNTY - Ashland. LEGAL - Not Applicable. Gates Lake near Glidden.
Habitat Improvement through Prescribed Burn Treatment Management Areas 8E, 8F, and 8G
CE

           *UPDATED*
- Wildlife, Fish, Rare plants  In Progress:
Scoping Start 02/15/2021 
Expected:09/2021
 
10/2021 Nicole Molitor
715-638-0272
nicole.g.molitor@usda.gov 
Description: Low-intensity prescribed fire will be used to meet goals and objectives for management areas 8E (Existing and Candidate Research Natural Areas), 8F (Special Management Areas), and 8G (Old Growth and Natural Feature Complexes).
Web Link:  http://www.fs.usda.gov/project/?project=59539
Location: UNIT - Great Divide Ranger District. STATE - Wisconsin. COUNTY - Ashland, Bayfield, Sawyer. LEGAL - Not Applicable. Several locations scattered throughout the district.
Veikko Cross-Country Trail Improvement and Development
CE

           *UPDATED*
- Recreation management  Developing Proposal
Est. Scoping Start 09/2021 
Expected:04/2022  05/2022 Katherine LeMoine
715-634-4821 x2326
katherine.lemoine@usda.gov 
Description: The Veikko Trail, an old cross-country ski trail in the St. Peter's Dome area developed by a local ski group, will be improved and realigned to fix drainage issues. Additional trail will be developed to connect to the St. Peter's Dome Trail network.
Web Link:  http://www.fs.usda.gov/project/?project=58459
Location: UNIT - Great Divide Ranger District. STATE - Wisconsin. COUNTY - Forest. LEGAL - Not Applicable. St. Peter's Dome area.
Back To Top

Chequamegon / Nicolet National Forest,   Lakewood-Laona Ranger District (excluding Projects occurring in more than one District)

R9 - Eastern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Jones Springs Project
EA

           *NEW LISTING*
- Recreation management  Developing Proposal
Est. Scoping Start 10/2021 
Expected:05/2022  05/2022 Evan Miller
715-674-4481
evanmiller@fs.fed.us 
Description: This recreation area was heavily impacted by the 2019 blowdown. This project is reviewing the recreation opportunities in the area to see if any changes are needed.
Web Link:  http://www.fs.usda.gov/project/?project=59902
Location: UNIT - Lakewood-Laona Ranger District. STATE - Wisconsin. COUNTY - Langlade, Oconto. LEGAL - Not Applicable. The Jones Springs area, legal T33N, R14 and R15E; T32N, R14 and 15 E.
Lakewood-Laona Plantation III
EA

           *NEW LISTING*
- Forest products  Developing Proposal
Est. Scoping Start 09/2021 
Expected:02/2022  05/2022 Benjamin Walker
907-826-1630
btwalker@fs.fed.us 
Description: Lakewood-Laona Ranger District is planning on thinning red pine plantation across the district.
Web Link:  http://www.fs.usda.gov/project/?project=59903
Location: UNIT - Lakewood-Laona Ranger District. STATE - Wisconsin. COUNTY - Forest, Langlade, Oconto. LEGAL - Not Applicable. Project is located at Townships 31-37 North and Ranges 12-17 East.
Lakewood-Laona Programmatic Salvage II
CE

           *NEW LISTING*
- Vegetation management (other than forest products)  Developing Proposal
Est. Scoping Start 09/2021 
Expected:11/2021  12/2021 John Lampereur
715-276-6333
jlampereur@fs.fed.us 
Description: This project would salvage timber on the district under certain criteria and design features. Each site will have a specialist review.
Web Link:  http://www.fs.usda.gov/project/?project=59925
Location: UNIT - Lakewood-Laona Ranger District. STATE - Wisconsin. COUNTY - Forest, Langlade, Oconto. LEGAL - Not Applicable. Lakewood-Laona Ranger District.
Twin Pines Additional Burn
CE

           *NEW LISTING*
- Vegetation management (other than forest products)  In Progress:
Scoping Start 06/29/2021 
Expected:10/2021
 
04/2022 Scott Linn
715-674-4481
slinn@fs.fed.us 
Description: This project would use burning to restore and maintain pine barrens in the southeast corner of the district.
Web Link:  http://www.fs.usda.gov/project/?project=59904
Location: UNIT - Lakewood-Laona Ranger District. STATE - Wisconsin. COUNTY - Oconto. LEGAL - Not Applicable. Located in the southeast corner of the district, legal is Township 31 Norther, Range 17East, Sections 27, 28, 33, and 34.
Back To Top

Chequamegon / Nicolet National Forest,   Medford-Park Falls Ranger District (excluding Projects occurring in more than one District)

R9 - Eastern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
John's Creek Gravel Pit Expansion
EA

           *UPDATED*
- Minerals and Geology  Developing Proposal
Est. Scoping Start 09/2021 
Expected:10/2022  11/2022 Greg Knight
715-748-4875 ext 7484826
greg.knight.3@usda.gov 
Description: This project consists of expansion of an existing gravel pit to meet road construction, re-construction, and maintenance needs in the project vicinity. This is an existing pit that has an additional source of gravel that has not been developed.
Web Link:  http://www.fs.usda.gov/project/?project=54736
Location: UNIT - Medford-Park Falls Ranger District. STATE - Wisconsin. COUNTY - Taylor. LEGAL - Not Applicable. Town of Grover, Township 31 North, Range 2 West, Section 7, Taylor County, Wisconsin.
Kidrick
EA

           *UPDATED*
- Forest products
- Vegetation management (other than forest products)
- Road management 
Developing Proposal
Est. Scoping Start 09/2021 
Expected:02/2022  03/2022 Leesha Howard-McCauley
715-748-4875 x37
leesha.howard-mccauley@usda.gov 
Description: This project is primarily a vegetation management project with focus on mid to late successional hardwood forest. Primary purpose is to maintain forest health and diversity. Project will also include a transportation analysis.
Web Link:  http://www.fs.usda.gov/project/?project=50889
Location: UNIT - Medford-Park Falls Ranger District. STATE - Wisconsin. COUNTY - Price. LEGAL - Not Applicable. Project is located in the northwest portion of the Forest within Taylor County in T32N, R2-3W and T33N, R1-3W.
Lake Eleven TS Snowmobile Trail Reroute
CE
- Recreation management  Developing Proposal
Est. Scoping Start 06/2021 
Expected:08/2021  09/2021 Gabriel Esquibel
715-762-5188
gabriel.esquibel@usda.gov 
Description: Permanently move the snowmobile trail to the Lake 11 Timber Sale haul road location to address wet areas that don't always freeze over.
Web Link:  http://www.fs.usda.gov/project/?project=57940
Location: UNIT - Medford-Park Falls Ranger District. STATE - Wisconsin. COUNTY - Price. LEGAL - Not Applicable. Project located in T31N, R2W, near Lake 11, and about 3 miles south of Perkinstown, WI.
Round Lake Fish Passage and Water Level Control
CE
- Watershed management  On Hold  N/A  N/A Jason Krebill
715-362-1300
jason.krebill@usda.gov 
Description: **On hold until water modelling/engineering plans are complete** The project will consist of reestablishing a two-way fish passage and reconnect the ecosystems of the Pike Lake Chain of Lakes and the South Fork Flambeau Rive
Web Link:  http://www.fs.usda.gov/project/?project=55358
Location: UNIT - Medford-Park Falls Ranger District. STATE - Wisconsin. COUNTY - Price. LEGAL - Not Applicable. T40N, R3E, Sections 23-26, Price County, WI.
Taylor County Hydrogeology Survey
CE

           *UPDATED*
- Special use management  In Progress:
Scoping Start 03/30/2021 
Expected:08/2021
 
08/2021 Greg Knight
715-748-4875 ext 26
gknight@fs.fed.us 
Description: USFS and WGNHS propose to study the hydrogeology of the North Fork Yellow River Watershed near the Bend ore deposit in Taylor to better understand the geology and groundwater connections in this area.
Web Link:  http://www.fs.usda.gov/project/?project=59449
Location: UNIT - Medford-Park Falls Ranger District. STATE - Wisconsin. COUNTY - Taylor. LEGAL - Not Applicable. T33N, R2W, Sections 34 & 35; T32N, R2W, Sections 2 & 3.
Winter Sports Road Electric Line Burial
CE

           *UPDATED*
- Special use management  Cancelled  N/A  N/A Kelly Scarbrough
715-362-1314
Kelly.Scarbrough@usda.gov 
Description: This is a proposal by Clark Electric Cooperative to convert about 4 1/4 miles of overhead electric line to underground electric wires within their existing utility corridor in order to provide a safer and more reliable electric service.
Web Link:  http://www.fs.usda.gov/project/?project=51504
Location: UNIT - Medford-Park Falls Ranger District. STATE - Wisconsin. COUNTY - Taylor. LEGAL - Not Applicable. Project is located in the Town of Grover (T32N, R2W) along Winter Sports Road (FR 119)starting at Spruce Lake Road going north to Beaver Creek Road (FR 121) and then a short distance east.
Wintergreen Snowshoe Trail Construction
CE
- Recreation management  Developing Proposal
Est. Scoping Start 10/2021 
Expected:12/2021  01/2022 Ann Dassow
715-748-4875 ext. 7484824
ann.dassow@usda.gov 
Description: Designation of a snowshoe trail system within the area of the Wintergreen Ski Trail area. Construction consists of clearing forest debris from marked trail.
Web Link:  http://www.fs.usda.gov/project/?project=57939
Location: UNIT - Medford-Park Falls Ranger District. STATE - Wisconsin. COUNTY - Price. LEGAL - Not Applicable. Within the Wintergreen Ski Trail System just north of State Hwy 70.
Back To Top

Chequamegon / Nicolet National Forest,   Northern Great Lakes Visitor Center (excluding Projects occurring in more than one District)

R9 - Eastern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
2021 Xcel Pole Replacement NGLVC
CE

           *UPDATED*
- Special use management  Completed  Actual: 04/02/2021  04/2021 Kelly Scarbrough
715-362-1314
Kelly.Scarbrough@usda.gov 
Description: Xcel Energy has requested to upgraded transmission line infrastructure within existing permitted area by replacing the single-circuit 34.5kV line on single-circuit poles with new double-circuit 34.5kV/34.5kV lines on double-circuit poles.
Web Link:  http://www.fs.usda.gov/project/?project=59577
Location: UNIT - Northern Great Lakes Visitor Center. STATE - Wisconsin. COUNTY - Bayfield. LEGAL - Not Applicable. Project is located along Terwilliger Rd. near the Northern Great Lakes Visitor Center. Bayfield County, WI at T. 47 N., R. 5 W., section 2.
Back To Top

Chequamegon / Nicolet National Forest,   Washburn Ranger District (excluding Projects occurring in more than one District)

R9 - Eastern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Bayfield Electric Hwy N Sec 31 Line Burial
CE

           *NEW LISTING*
- Special use management  Developing Proposal
Est. Scoping Start 04/2021 
Expected:06/2021  06/2021 Kelly Scarbrough
(715)362-1314
Kelly.Scarbrough@usda.gov 
Description: The Forest has received a request to bury about 1,800 feet of existing overhead powerline near County Hwy N. Proposal addresses recent changes from high water in this area including raising/widening of County Hwy N and dying trees.
Web Link:  http://www.fs.usda.gov/project/?project=59914
Location: UNIT - Washburn Ranger District. STATE - Wisconsin. COUNTY - Bayfield. LEGAL - T45N, R8W, Section 31, Bayfield County, WI . About 13 miles west of Drummond, WI. Along County Highway N.
Enbridge Energy Limited Partnership SUP
CE

           *UPDATED*
- Special use management  In Progress:
Scoping Start 12/07/2016 
Expected:11/2021
 
12/2021 Jennifer Maziasz
715-373-2667
comments-eastern-chequamegon-nicolet-washburn@usda.gov 
Description: The proposal is to re-issue a special use authorization for a new term for Enbridge Energy Limited Partnership's existing pipeline system, pumping station, and associated improvements.
Web Link:  http://www.fs.usda.gov/project/?project=44889
Location: UNIT - Washburn Ranger District. STATE - Wisconsin. COUNTY - Bayfield. LEGAL - Not Applicable. Project includes 11.5 miles of existing pipeline system, the pumping station, and associated improvements on Forest Service lands north of US Highway 2.
North Country Trail - Drummond Connector
CE

           *NEW LISTING*
- Recreation management  In Progress:
Scoping Start 06/07/2021 
Expected:07/2021
 
07/2021 Sarah Holmes
715-373-2667
sarah.holmes@usda.gov 
Description: Proposal is to open one-mile of trail on an old railroad grade from the North Country Trail to the Town of Drummond. The action involves brushing, tree removal and sign installation.
Web Link:  http://www.fs.usda.gov/project/?project=59917
Location: UNIT - Washburn Ranger District. STATE - Wisconsin. COUNTY - Bayfield. LEGAL - T45N, R7W, Section 33, Bayfield County, WI. Trail would be located between the North Country Trail and the Town of Drummond. The connector trail includes an old railroad grade and the northwest section of the Drummond Woods Trail.
Wildcat Motorized Trail Projects
CE

           *NEW LISTING*
- Recreation management  Developing Proposal
Est. Scoping Start 04/2021 
Expected:09/2021  10/2021 Sarah Holmes
715-373-2667
sarah.holmes@usda.gov 
Description: Two actions: 1)Add 4 miles of ATV/UTV use from Town of Drummond south to Lake Owen Station Road (includes trail stabilization on hills); 2) a 0.11-mile reroute (on snowmobile only portion of trail) to avoid a lowland area which is not freezing.
Web Link:  http://www.fs.usda.gov/project/?project=59920
Location: UNIT - Washburn Ranger District. STATE - Wisconsin. COUNTY - Bayfield. LEGAL - Not Applicable. Wildcat Motorized trail south of the Town of Drummond to Lake Owen Station Road.
In accordance with Federal civil rights law and U.S. Department of Agriculture (USDA) civil rights regulations and policies, the USDA, its Agencies, offices, and employees, and institutions participating in or administering USDA programs are prohibited from discriminating based on race, color, national origin, religion, sex, gender identity (including gender expression), sexual orientation, disability, age, marital status, family/parental status, income derived from a public assistance program, political beliefs, or reprisal or retaliation for prior civil rights activity, in any program or activity conducted or funded by USDA (not all bases apply to all programs). Remedies and complaint filing deadlines vary by program or incident.

Persons with disabilities who require alternative means of communication for program information (e.g., Braille, large print, audiotape, American Sign Language, etc.) should contact the responsible Agency or USDA’s TARGET Center at (202) 720-2600 (voice and TTY) or contact USDA through the Federal Relay Service at (800) 877-8339. Additionally, program information may be made available in languages other than English.

To file a program discrimination complaint, complete the USDA Program Discrimination Complaint Form, AD-3027, found online at http://www.ascr.usda.gov/complaint_filing_cust.html and at any USDA office or write a letter addressed to USDA and provide in the letter all of the information requested in the form. To request a copy of the complaint form, call (866) 632-9992. Submit your completed form or letter to USDA by:

(1) mail: U.S. Department of Agriculture
Office of the Assistant Secretary for Civil Rights
1400 Independence Avenue, SW
Washington, D.C. 20250-9410;

(2) fax: (202) 690-7442; or

(3) email: program.intake@usda.gov.

USDA is an equal opportunity provider, employer, and lender.