Schedule of Proposed Actions (SOPA) |
|||||
| This report contains the best available information at the time of publication. Questions may be directed to the Project Contact. | |||||
|
Report Contents (click to jump to a section) : - Projects Occurring Nationwide - Projects Occurring in more than one Region (excluding Nationwide) - R4 - Intermountain Region, Occurring in more than one Forest (excluding Regionwide) - R4 - Intermountain Region, Caribou-Targhee National Forest, Occurring in more than one District (excluding Forestwide) - R4 - Intermountain Region, Caribou-Targhee National Forest, Ashton/Island Park (excluding Projects occurring in more than one District) - R4 - Intermountain Region, Caribou-Targhee National Forest, Dubois Ranger District (excluding Projects occurring in more than one District) - R4 - Intermountain Region, Caribou-Targhee National Forest, Montpelier Ranger District (excluding Projects occurring in more than one District) - R4 - Intermountain Region, Caribou-Targhee National Forest, Palisades Ranger District (excluding Projects occurring in more than one District) - R4 - Intermountain Region, Caribou-Targhee National Forest, Soda Springs Ranger District (excluding Projects occurring in more than one District) - R4 - Intermountain Region, Caribou-Targhee National Forest, Teton Basin Ranger District (excluding Projects occurring in more than one District) - R4 - Intermountain Region, Caribou-Targhee National Forest, Westside Ranger District (excluding Projects occurring in more than one District) | |||||
Projects Occurring Nationwide |
|||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|---|---|---|---|---|---|
|
Gypsy Moth Management in the United States: A Cooperative Approach EIS |
- Vegetation management (other than forest products) |
In Progress: DEIS NOA in Federal Register 09/19/2008 Est. FEIS NOA in Federal Register 12/2011 |
Expected:03/2012 |
01/2013 |
Noel Schneeberger 610-557-4121 nschneeberger@fs.fed.us |
| Description: The USDA Forest Service and Animal and Plant Health Inspection Service are analyzing a range of strategies for controlling gypsy moth damage to forests and trees in the United States.
Web Link: http://www.na.fs.fed.us/wv/eis/ |
|||||
| Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. Nationwide. | |||||
|
Land Management Planning Rule EIS |
- Regulations, Directives, Orders | Completed | Actual: 03/23/2012 | 12/2011 |
Brenda Halter-Glenn 202-260-9400 bhalterglenn@fs.fed.us |
| Description: The Department of Agriculture proposes to promulgate a new planning rule, which will set out the process for development, revision, and amendment of National Forest System land management plans.
Web Link: http://www.fs.usda.gov/planningrule |
|||||
| Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. Agency-wide Rule. | |||||
|
Nationwide Aerial Application of Fire Retardant on National Forest System Lands. EIS |
- Regulations, Directives, Orders | Completed | Actual: 12/13/2011 | 01/2012 |
Glen Stein 801-200-2703 gstein@fs.fed.us |
| Description: The Forest Service will prepare a programmatic environmental impact statement for the continued nationwide aerial application of fire retardant on National Forest System lands.
Web Link: http://www.fs.fed.us/fire/retardant/index.html |
|||||
| Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. Nationwide. | |||||
| Back To Top | |||||
Projects Occurring in more than one Region (excluding Nationwide) |
|||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Gateway West 230/500 kv Transmission Line Project EIS |
- Special use management |
In Progress: DEIS NOA in Federal Register 07/29/2011 Est. FEIS NOA in Federal Register 09/2012 |
Expected:09/2012 |
11/2012 |
Misty Hays 307-358-4690 mahays@fs.fed.us |
| Description: Idaho Power and Rocky Mountain Power propose to construct electric transmission lines from the proposed Windstar Substation near the Dave Johnston Power Plant at Glenrock, WY to the proposed Hemingway substation near Melba, Idaho
Web Link: http://www.wy.blm.gov/nepa/cfodocs/gateway_west/ |
|||||
| Location: UNIT - Douglas and Thunder Basin Ranger District, Montpelier Ranger District. STATE - Idaho, Wyoming. COUNTY - Bear Lake, Albany, Converse, Natrona. Montpelier District, CTNF - northern most corridor designated in the Caribou NF Plan, Doulgas Distict MBRNF northern most corridor designated in the MBR Plan. | |||||
|
Mountain States Transmission Intertie EIS |
- Special use management |
In Progress: NOI in Federal Register 08/20/2008 Est. DEIS NOA in Federal Register 01/2012 |
Expected:12/2012 |
03/2013 |
Patty Bates 406-683-3979 pbates@fs.fed.us |
| Description: Issue easement to Northwestern Energy to construct and maintain a 500 KV electricity transmission line on National Forest System lands in Montana and Idaho. BLM is lead agency and Forest Service is cooperating agency. | |||||
| Location: UNIT - Butte Ranger District, Jefferson Ranger District, Pintler Ranger District, Dubois Ranger District, Dillon Ranger District. STATE - Idaho, Montana. COUNTY - Clark, Beaverhead, Deer Lodge, Jefferson, Silver Bow. Various locations depending upon the alternative route locations. | |||||
| Back To Top | |||||
R4 - Intermountain Region, Occurring in more than one Forest (excluding Regionwide) |
|||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Greater Sage-grouse Management Direction EIS *NEW LISTING* |
- Land management planning - Wildlife, Fish, Rare plants |
In Progress: NOI in Federal Register 12/09/2011 Est. DEIS NOA in Federal Register 04/2013 |
Expected:08/2014 |
09/2014 |
Glen Stein 801-625-5281 gstein@fs.fed.us |
| Description: The purpose of this project is to prepare environmental impact statements (EISs) and supplemental environmental impact statements to incorporate greater sage-grouse conservation measures into Bureau of Land Management land use plans and Forest Plans. | |||||
| Location: UNIT - Boise National Forest All Units, Salmon-Challis National Forest All Units, Sawtooth National Forest All Units, Caribou-Targhee National Forest All Units. STATE - Idaho. COUNTY - Adams, Blaine, Bonneville, Camas, Caribou, Cassia, Elmore, Fremont, Madison. Boise NF, Salmon-Challis NF, Caribou-Targhee NF, Sawtooth NF, Curlew NG. | |||||
|
Incorporating Greater Sage-grouse Conservation Measures into Land Management Plans (Idaho) EIS |
- Land management planning - Wildlife, Fish, Rare plants |
Developing Proposal Est. Notice of Adjustment 12/2011 |
Expected:05/2014 | 06/2014 |
Clinton McCarthy 801-625-5671 cmccarthy01@fs.fed.us |
| Description: The Forest Service will be a cooperating agency with the BLM (lead agency) in preparing programmatic EISs to incorporate greater sage-grouse conservation measures into land management plans (Sawtooth, Caribou, Curlew) through plan amendments
Web Link: http://www.blm.gov/wo/st/en/prog/more/sagegrouse/western.html |
|||||
| Location: UNIT - Sawtooth National Forest All Units, Montpelier Ranger District, Soda Springs Ranger District, Westside Ranger District. STATE - Idaho, Utah, Wyoming. COUNTY - Bannock, Bear Lake, Blaine, Boise, Bonner, Camas, Caribou, Cassia, Custer, Elmore, Franklin, Oneida, Power, Twin Falls, Box Elder, Cache, Lincoln. UNIT - Sawtooth NF (ID, UT); Caribou (ID UT, WY) and Curlew NG (ID) portions of the Caribou-Targhee NF; multiple counties involved. | |||||
| Back To Top | |||||
Caribou-Targhee National Forest, Occurring in more than one District (excluding Forestwide) |
R4 - Intermountain Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Proposed Targhee Revised Forest Plan Amendment EIS |
- Land management planning |
In Progress: NOI in Federal Register 10/29/2010 Est. DEIS NOA in Federal Register 03/2012 |
Expected:06/2012 |
10/2012 |
Megan Bogle 208-354-6613 mbogle@fs.fed.us |
| Description: Proposes to amend the 1997 Revised Forest Plan for the Targhee portion of the Forest to address direction for "old-growth" and "late-seral" forested vegetation, snags and wildlife habitat for select cavity-nesting species. | |||||
| Location: UNIT - Palisades Ranger District, Teton Basin Ranger District, Dubois Ranger District, Ashton/Island Park. STATE - Idaho, Wyoming. COUNTY - Bonneville, Butte, Clark, Fremont, Jefferson, Lemhi, Madison, Teton, Teton, Lincoln. Targhee portion of the Caribou-Targhee National Forest. | |||||
|
Teton Communication Electronic Site CE |
- Facility management |
In Progress: 215 Comment Period Legal Notice 10/01/2011 |
Expected:07/2012 |
08/2012 |
Glenn Lackey 208-547-1105 glackey@fs.fed.us |
| Description: Proposal to place a 140+ foot electronic communications tower with building to house equipment.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=36989 |
|||||
| Location: UNIT - Palisades Ranger District, Soda Springs Ranger District. STATE - Idaho. COUNTY - Bonneville, Caribou. LEGAL - North end of Black Mountain near the head of Trout Creek in the South end of Section 24, T3S, R45E. Approximately 2 miles North of the existing electonic site at Black Mountain, Bonneville County, Idaho; approximately 12 miles North and West of Etna, Wyoming. | |||||
|
Wells Canyon, Stewart Canyon and Green Mountain Sheep Grazing Reauthorization EA |
- Grazing management |
In Progress: 215 Comment Period Legal Notice 10/22/2010 |
Expected:04/2012 |
06/2012 |
Kevin Parker 208-678-0430 kparker@fs.fed.us |
| Description: Re-authorize sheep grazing on the Wells Canyon, Stewart Canyon, and Green Mountain sheep allotments | |||||
| Location: UNIT - Montpelier Ranger District, Soda Springs Ranger District. STATE - Idaho. COUNTY - Caribou. LEGAL - Townships 9 and 10 South, Ranges 44 and 45 East. 15,500 acres along the east side of the Caribou National Forest, within the Montpelier and Soda Springs Ranger Districts. | |||||
| Back To Top | |||||
Caribou-Targhee National Forest, Ashton/Island Park (excluding Projects occurring in more than one District) |
R4 - Intermountain Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Bear Gulch Road Closure (Forest Road 159) EA |
- Wildlife, Fish, Rare plants - Road management |
In Progress: 215 Comment Period Legal Notice 02/25/2011 |
Expected:04/2012 |
07/2012 |
Lee Mabey 208-557-5784 lmabey@fs.fed.us |
| Description: Close the .5 mile segment of Bear Gulch Road159 and create a trail. The road is in the bottom of the drainage and cannot be maintainted to a usable standard. Closure is proposed to protect resource values. | |||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - T. 10 N. R 44 E. Sec 31, 32. Road is located at the site of the old Bear Gulch Ski Hill off of the Mesa Falls Scenic Byway, Northeast of Ashton, ID. | |||||
|
Big Springs Recreation Residence Tract Special Use Permit Reissuance CE *NEW LISTING* |
- Special use management |
In Progress: Scoping Start 02/13/2012 |
Expected:09/2012 |
10/2012 |
Brandon Burke 208-652-1201 brandonburke@fs.fed.us |
| Description: The proposed action is to renew 20-year term special use permits for 12 recreation residence lots in the Big Springs Recreation Residence Tract. This action is not proposing any new lots, tracts, facilities, or alterrations of existing facilites.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=38372 |
|||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - T.14N., R.44E. Section 33. BIg Springs Recreation Residence Tract. | |||||
|
FairPoint Communications Fiber Optic Special Use Permit CE *NEW LISTING* |
- Special use management |
In Progress: Scoping Start 02/08/2012 |
Expected:04/2012 |
07/2012 |
Bill Davis 208-652-1228 bdavis@fs.fed.us |
| Description: This project would install buried fiber optic cable from an existing cable location at South Antelope Flat Road to the Big Bend Ridge Communications site at the top of the Ashton Hill.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=38384 |
|||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - T.10N., R.42E., Sections 13 & 24 and T.10N., R.43E., Section 19. The project is located along Highway 20 beginning at the South Antelope Road and ending at the Big Bend Rdige Communication Site. | |||||
|
Fish Creek Restoration Project CE |
- Wildlife, Fish, Rare plants - Watershed management |
In Progress: Scoping Start 02/25/2011 |
Expected:03/2012 |
08/2012 |
Lee Mabey 208-557-5784 lmabey@fs.fed.us |
| Description: Restore this spring creek a tributary to the Henrys Fork by placing native sedge mats within the stream creating new banks narrowing the channel, increasing velocities and sediment transport to improve trout spawning, rearing and overwintering. | |||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - The stream that feeds into and flows out of the Fish Pond on Harriman State Park. T. 11N., R. 43E. Sections 6. | |||||
|
Green Canyon Road Fuelbreak EA |
- Fuels management |
In Progress: 215 Comment Period Legal Notice 07/08/2011 |
Expected:05/2012 |
07/2012 |
Robert Albano 208-558-7301 ralbano@fs.fed.us |
| Description: Masticate dead and down fuels and remove ladder fuels along the south side of the Green Canyon Road (FS Road # 167) for approx. 4 miles. The area would be 200 feet from the borrow pit. | |||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - T.12N., R.42E., Sections 32-35. South side of the Green Canyon Road (FS Road #167) from the junction of Hwy 20 to approx. 4 miles west. Cutting would occur 200 feet from the borrow pit. | |||||
|
Head of Buffalo River Road Realignment Project CE |
- Wildlife, Fish, Rare plants - Watershed management - Road management |
In Progress: Scoping Start 02/25/2011 |
Expected:03/2012 |
07/2012 |
Lee Mabey 208-557-5784 lmabey@fs.fed.us |
| Description: Road is one mile long, project to shift ½ mile of road out of bottom to promote better drainage and less sediment delivery to the Buffalo River, the native surfaced road will be graveled. The abandoned road will be water barred and seeded. | |||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - The access road to float the Buffalo River starting at the springhead. T. 13N., R. 44E. Sections 21 and 28. | |||||
|
Horseshoe Lake, Sheep Falls, Harriman Fish Pond, and Coffee Pot CE *NEW LISTING* |
- Recreation management |
In Progress: Scoping Start 03/02/2012 |
Expected:06/2012 |
08/2012 |
Bill Davis 208-652-1228 bdavis@fs.fed.us |
| Description: This project seeks to rehabilitate dispersed recreation sites, imporve access roads, rebuild trails, and define parking areas at various locations on the Ashton/Island Park District.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=38369 |
|||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - Horseshoe Lake T.10N., R. 46E., Sec 26; Sheep Falls T.9N., R.46E. Secs 19 & 30 and T.9N., R.45E., Sec 25; Harriman Fish Pond T.12N., R.43E., Sec 31; Coffee Pot Trail T.14N., R.43E., Sec 33. The projects are located near Horseshoe Lake, Sheep Falls - FS Road 363, Harriman Fish Pond and Coffee Pot Trail. | |||||
|
Island Park Community Non-Motorized Trail CE *NEW LISTING* |
- Recreation management |
In Progress: Scoping Start 03/02/2012 |
Expected:06/2012 |
08/2012 |
Jarrod Hansen 208-652-1212 jarrodhansen@fs.fed.us |
| Description: The Island Park Non-Motorized Trail Project is a route that would connect Harriman State Park and Henry's Lake. This concept was identified by the Island Park Gem Team and the Sawtell Fun Run Committe partnered with the Ashton/IP RD.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=38371 |
|||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - Kenny Crk Phase T.15N., R.43E., Secs 30, 31, 32, 33 - beginning at F.S. Rd #463 ending at F.S. Rd #455;Box Canyon Phase T.13N., R.42E., Sec 8 - south end of Box Canyon Trl #029 ending at F.S. Rd. #134. The trail is located between Last Chance and Henry's Lake near Island Park, ID. | |||||
|
Island Park Horse Pasture CE |
- Grazing management |
Developing Proposal Est. Scoping Start 09/2012 |
Expected:12/2012 | 05/2013 |
Jim Cox 208-558-7301 jcox@fs.fed.us |
| Description: Improve forage for Forest livestock. | |||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - T.13N., R.43E., Section 27. The pasture is 40 acres in size and located along the northeast boundary of the Island Park Ranger Station Administrative Site. | |||||
|
Macks Inn Sewer Expansion EA |
- Special use management |
Developing Proposal Est. Scoping Start 03/2012 |
Expected:07/2012 | 08/2012 |
Bill Davis 208-652-1228 bdavis@fs.fed.us |
| Description: Fremont County is seeking to expand the Macks Inn Sewer Treatment Facility by increasing the irrigation field (not the leach field) by approximately 50 acres to handle increased needs in the North Island Park area. | |||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - T.14N., R.44E., Section 30. The project is located south of the North Big Springs Road and southeast of Island Park Lodge. | |||||
|
North Island Park WUII EA |
- Forest products - Vegetation management (other than forest products) - Fuels management |
On Hold | N/A | N/A |
Jim Cox 208-558-7301 jcox@fs.fed.us |
| Description: Proposes to reduce hazardous fuels adjacent to private property on approximately 950 acres. A fuel break would be created in three treatment units by thinning, hand-piling, commercial logging, firewood gathering and prescribed burning. | |||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - Bighorn Hills Estates T.15N., R.44E., Secs 6 & 7; Bootjack T.15N., R.43E., Secs 28-30 & T.15N. R.42E. Sec 25; Meadow Cr. T.14N., R.44E., Secs 3, 4, 10, 15, 21, & 22; Moose Cr. T.13N., R.44E., Sec 4. North Island park area near Henry's Lake - Bighorn Hills Estate, Bootjack area, Meadow Creek area, and Moose Creek Summer Homes. | |||||
|
Porcupine Pasture Prescribed Burn EA |
- Grazing management - Fuels management |
In Progress: Scoping Start 11/29/2011 Est. Objection Period Legal Notice 06/2012 |
Expected:07/2012 |
07/2013 |
Ben Krupski 208-558-7301 bkrupski@fs.fed.us |
| Description: Removal of conifers from the Porcupine Guard Station Pasture to rejuvenate grasses and forbs. | |||||
| Location: UNIT - Ashton/Island Park. STATE - Idaho. COUNTY - Fremont. LEGAL - T.9N., R.44E., Section 23. The analysis area is located at the Porcupine Guard Station on the Ashton/Island District. The Guard Station is adjacent to the Potpourri subdivision. | |||||
| Back To Top | |||||
Caribou-Targhee National Forest, Dubois Ranger District (excluding Projects occurring in more than one District) |
R4 - Intermountain Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Corral Creek Dam Rehabilitation and Fish Passage CE |
- Wildlife, Fish, Rare plants - Watershed management |
In Progress: Scoping Start 12/19/2011 |
Expected:04/2012 |
07/2012 |
Shane Jacobson 208-374-5422 sqjacobson@fs.fed.us |
| Description: Improve the spillway of the Corral Creek dam to facilitate natural stream function, improve stabilization of the dam, and to provide for fish passage. Includes maintaining a pond in place of the reservoir to maintain public fishing opportunities.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=37886 |
|||||
| Location: UNIT - Dubois Ranger District. STATE - Idaho. COUNTY - Clark. LEGAL - T12N, R37E, Section 12. 8 miles east of Spencer, Idaho. | |||||
|
Eastside Trailhead Improvements CE |
- Recreation management - Watershed management |
Developing Proposal Est. Scoping Start 06/2012 |
Expected:01/2013 | 07/2013 |
Jeffrey Liday 208-374-5422 ext. 119 jliday@fs.fed.us |
| Description: Relocate trailheads or perform heavy maintenance at the Bear Gulch, Coal Mine, Pete Creek & Trail Creek trailheads to improve safety and reduce erosion/ sediment loading to streams. Expand surface area and add barriers if needed. | |||||
| Location: UNIT - Dubois Ranger District. STATE - Idaho. COUNTY - Clark. LEGAL - 019 – Bear Gulch T14N R3W S4NWCorner, 023- Coal Mine T14N R3W S24NWCorner, 010- Pete Creek T14N R4W S23SE Corner, and 029- Trail Creek T14N R3W S4SE corner. Trailheads at the end of forest service roads 019- Bear Gulch, 023- Coal Mine, 010- Pete Creek, and 029- Trail Creek. | |||||
|
Whitebark Pine Protection CE |
- Vegetation management (other than forest products) |
In Progress: Scoping Start 11/23/2011 |
Expected:04/2012 |
06/2012 |
Cathey Hardin 208-558-4207 chardin@fs.fed.us |
| Description: Cut, pull back and pile slash from conifers that is located within a 50 to 100 foot radius of mature, cone producing whitebark pine trees. This will reduce the competition and create a fuel break. Slash would be piled and possibly burned. | |||||
| Location: UNIT - Dubois Ranger District. STATE - Idaho. COUNTY - Clark. LEGAL - Boatman: T14N, R37E, Sections 17-22, 27 and 28. Lone Pine: T13N, R37E, Sections 21-28, and T13N, R38E, Sections 19, 20, 29 ,30. Table Mountain: T14N, R37E, Sections 13 and T14N, R38E, Sections 15-22,. There are three different area identified for treatment on the Dubois Ranger District; Boatman, Lone Pine and Table Mountain. | |||||
| Back To Top | |||||
Caribou-Targhee National Forest, Montpelier Ranger District (excluding Projects occurring in more than one District) |
R4 - Intermountain Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Cache Roads Hazardous Fuels Treatment EA |
- Vegetation management (other than forest products) - Fuels management - Road management |
Developing Proposal Est. Scoping Start 11/2012 |
Expected:03/2013 | 07/2013 |
Dennis Duehren 208-847-0375 dduehren@fs.fed.us |
| Description: Treat 3900 acres of hazardous fuels 300 feet off of open forest roads. Smaller diameter conifer and dead and down fuels will be cut, piled and burned to reduce hazardous fuels. | |||||
| Location: UNIT - Montpelier Ranger District. STATE - Idaho. COUNTY - Bear Lake, Caribou, Franklin. LEGAL - The project is located in T9S to T16S, R40E to R43E, and all sections. All open forest roads on the Cache Forest that is administered by the Caribou National Forest. | |||||
|
Ephraim Valley Aspen Treatment CE |
- Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management |
In Progress: 215 Comment Period Legal Notice 05/31/2007 |
Expected:01/2013 Actual: 11/21/2008 |
07/2013 |
Devon Green 208-547-1116 dhgreen@fs.fed.us |
| Description: Use prescribed fire to restore aspen, by killing invading conifer on approximately 500 acres, and increase shrub diversity on approximately 150 acres to improve wildlife habitat in an 800 acre project area. | |||||
| Location: UNIT - Montpelier Ranger District. STATE - Idaho. COUNTY - Caribou. LEGAL - T10S, R46E, Sec 29-32. Boise Meridian. Ridge between Ephraim Valley and Elk Valley within the Gannett Hills between Crow Creek and the Wyoming State line. | |||||
|
Main Canyon Vegetation Management Project EA |
- Forest products - Vegetation management (other than forest products) - Fuels management |
Developing Proposal Est. Scoping Start 11/2012 |
Expected:04/2013 | 07/2013 |
Jane Rushane 208-847-0375 jrushane@fs.fed.us |
| Description: Use prescribed fire and timber harvest to change species composition and structure on 3600 acres in several different vegetation cover types in the Main Canyon area. | |||||
| Location: UNIT - Montpelier Ranger District. STATE - Idaho. COUNTY - Franklin. LEGAL - Township 12 S, Range 41 E Sections 1, 2, 3, 10-15, 22 and 28. Approximately 13 mile south of Grace, Idaho. Access is via Forest roads 440 and 442. | |||||
|
Strawberry Aspen Treatment CE |
- Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management |
In Progress: 215 Comment Period Legal Notice 10/23/2009 |
Expected:01/2013 |
07/2013 |
Dennis Duehren 208-847-0375 dduehren@fs.fed.us |
| Description: Use prescribed fire and mechanical thinning to reduce conifer encroachment in aspen forest (1400 acres), to improving wildlife habitat and reducing fuel loading in the 2600 acre project area. | |||||
| Location: UNIT - Montpelier Ranger District. STATE - Idaho. COUNTY - Franklin. LEGAL - T12S, R42E, Sec 30-31, T12S,R41E, Sec 36, T13S, R42E, Sec 6 and T13S, R41E, Sec 1,6,7,12 Boise Meridian. Southwest of Montpelier, ID on Hwy. 30 in Emigration Canyon. | |||||
|
Telegraph Hollow WUI EA |
- Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management |
In Progress: Scoping Start 06/21/2010 Est. 215 Comment Period Legal Notice 01/2013 |
Expected:03/2013 |
07/2013 |
Dennis Duehren 208-847-0375 dduehren@fs.fed.us |
| Description: Reduce understory tree and brush densisites to change stand age, composition and structure to mimic historic fire regimes and improve wildlife habitat. Masticator would be used and slash piled/burned. No commercial harvest or road construction. | |||||
| Location: UNIT - Montpelier Ranger District. STATE - Idaho. COUNTY - Bear Lake. LEGAL - Township 14S Range 42E Sections 13,24. 15 miles Southwest of Montpelier, Idaho in Bloomington Canyon. | |||||
| Back To Top | |||||
Caribou-Targhee National Forest, Palisades Ranger District (excluding Projects occurring in more than one District) |
R4 - Intermountain Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Carlton Cutoff Trailhead Relocation CE *NEW LISTING* |
- Recreation management - Watershed management |
Developing Proposal Est. Scoping Start 03/2012 |
Expected:04/2012 | 06/2012 |
David Woodcock 208-523-1412 dwoodcock@fs.fed.us |
| Description: Move Trailhead a quarter (1/4) mile up to Moody Meadows from current location. Trail will be relocated parallel to FS Road #218. Total reroute will be a total of .35 of a mile.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=38394 |
|||||
| Location: UNIT - Palisades Ranger District. STATE - Idaho. COUNTY - Madison. LEGAL - Secs 12 and 13 T4N, R42E. Project is located off Forest Service Road 218 at Ruby Creek. | |||||
|
Flatiron Aspen Improvement Project CE |
- Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management |
In Progress: Scoping Start 08/11/2011 |
Expected:04/2012 |
07/2012 |
Spencer Johnston 208-523-1412 sdjohnston@fs.fed.us |
| Description: Use prescribed fire to treat 1533 acres to improve the declining aspen population and decadent brush species to create a diversity of age classes for wildlife and critical summer range for big game species as well as for public safety. | |||||
| Location: UNIT - Palisades Ranger District. STATE - Idaho. COUNTY - Bonneville. Unit- Palisades Ranger District. State- Idaho. County-Bonneville. Legal- Township 1N, Range 44E, Sections 19, 20, 28-30. The project area is located 5 miles south of Swan Valley, Idaho. | |||||
|
Hoffman Area Mountain Pine Beetle Infested Tree Removal Project EA |
- Recreation management - Fuels management - Facility management |
In Progress: Scoping Start 11/30/2010 Est. Objection Period Legal Notice 06/2012 |
Expected:07/2012 |
09/2012 |
Randy Griffith 208-542-5812 rsgriffith@fs.fed.us |
| Description: Remove lodgepole pine trees infested with Mountain Pine Beetles in the area around Hoffman Summer Home and McCoy Creek Campgrounds, which are dead, dying, and hazard trees.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=34861 |
|||||
| Location: UNIT - Palisades Ranger District. STATE - Idaho. COUNTY - Bonneville. LEGAL - T3S, R46E, Sec.5, and 8. The area surrounding of the Hoffman Summer Home and McCoy Creek Campgrounds, near the Southwest shore of Palisades Reservoir. | |||||
| Back To Top | |||||
Caribou-Targhee National Forest, Soda Springs Ranger District (excluding Projects occurring in more than one District) |
R4 - Intermountain Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Caribou Archery Road Relocation CE |
- Wildlife, Fish, Rare plants - Watershed management |
In Progress: Scoping Start 01/01/2012 |
Expected:04/2012 |
09/2012 |
Jack Isaacs 208-547-4356 jisaacs@fs.fed.us |
| Description: Relocate 0.6 mile of FR50297, Caribou Archery Road, farther away from a perennial tributary to Trail Creek. Construct parking for 20-30 vehicles at end of new road. Decommission old road.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=36404 |
|||||
| Location: UNIT - Soda Springs Ranger District. STATE - Idaho. COUNTY - Caribou. LEGAL - N.1/2 Sec. 29, T. 8S., R. 43E., Boise Meridian. At North end of Monsanto Plant in Soda Springs on Hwy 34, drive East on Trail Creek Rd 6 miles. Take right at fork at "Y" at hunting lodge. Drive down the hill 1.5 miles, turn right FS50297. | |||||
|
Dairy Syncline Phosphate Mine EIS |
- Minerals and Geology |
In Progress: NOI in Federal Register 04/13/2010 Est. DEIS NOA in Federal Register 04/2013 |
Expected:04/2014 |
09/2014 |
Jack Isaacs 208-547-4356 jisaacs@fs.fed.us |
| Description: Analyze a proposed new phosphate mine plan and associated projects and infrastructure on existing lease I-28115 and I-0258, encompassing approximately 1,500 acres on lease and approximately 400 acres off lease. Considers land exchange proposal.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=27958 |
|||||
| Location: UNIT - Soda Springs Ranger District. STATE - Idaho. COUNTY - Bear Lake, Caribou. LEGAL - Portions of T9S, R44E Sections 6, 7, 16-21, 28, 29, 32, 33. East flank of the Aspen Range, approximately 12 miles east of Soda Springs, Idaho. | |||||
|
Homestead Prescribed Burn CE |
- Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management |
Developing Proposal Est. Scoping Start 12/2012 |
Expected:06/2013 | 09/2013 |
Devon Green 208-547-1116 dhgreen@fs.fed.us |
| Description: The Soda/Montpelier zone of the Caibou-Targhee proposes to burn mountain brush, small stands of conifer and aspen in the Homestead unit of the Jackknife cattle allotments. Burn is expected to improve big game species and age diversity.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=36309 |
|||||
| Location: UNIT - Soda Springs Ranger District. STATE - Idaho. COUNTY - Caribou. Homestead unit of the Jackknife Cattle Allotment. | |||||
|
Hooper Springs Transmission Line EIS |
- Special use management |
In Progress: NOI in Federal Register 07/08/2010 Est. DEIS NOA in Federal Register 08/2012 |
Expected:01/2013 |
06/2013 |
Glenn Lackey 208-677-8303 glackey@fs.fed.us |
| Description: Build a new 20 mile double circuit 115-KV powerline from Soda Springs to the existing powerline in Lanes Creek. The new line will cross about 2 miles of the Forest. Alternate route that avoids all National Forest System lands is being considered.
Web Link: http://www.efw.bpa.gov/environmental_services/Document_Library/HooperSprings/ |
|||||
| Location: UNIT - Soda Springs Ranger District. STATE - Idaho. COUNTY - Caribou. LEGAL - T 7 S, R 44 E, Sections 19-22, 26-29. Across the Forest, just south of the Blackfoot River. | |||||
|
Husky 1 - North Dry Ridge Mine EIS |
- Minerals and Geology |
Developing Proposal Est. NOI in Federal Register 06/2012 |
Expected:11/2016 | 12/2016 |
Jack Isaacs 208-547-4356 jisaacs@fs.fed.us |
| Description: Nu-West Industries, Inc., submitted a Mine and Reclamation Plan (MRP) which proposes new open-pit phosphate mining operations on federal leases I-05549, I-8289, I-04 and some adjacent private lands. It also proposes lease mods. and several S.U.A.s.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=37878 |
|||||
| Location: UNIT - Soda Springs Ranger District. STATE - Idaho. COUNTY - Caribou. LEGAL - T. 7 S., R. 44 E., Sections: 16, 17, 20, 21, 28, 33 & 34. T. 8 S., R. 44 E., Sections: 3, 4, 10, 11, 14, 15, 23, 24 & 25. T. 8 S., R. 45 E., Sections: 30, 31 & 32. Proposed mining operations would be located in Caribou County, ID; approximately 15 miles Northeast of Soda Springs, ID. | |||||
|
Rasmussen Valley Geotechnical Drilling CE |
- Minerals and Geology |
Developing Proposal Est. Scoping Start 01/2012 |
Expected:03/2012 | 03/2012 |
Jack Isaacs 208-547-4356 jisaacs@fs.fed.us |
| Description: Nu-West Industries, Inc., submitted a Geotechnical Study Plan which proposes to install several shallow geotechnical borings including piezometers on National Forest land adjacent to Federal Leases I-05975 in support of the Rasmussen Valley Mine EIS.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=37873 |
|||||
| Location: UNIT - Soda Springs Ranger District. STATE - Idaho. COUNTY - Caribou. LEGAL - T. 7 S., R. 44 E., Sections: 5 & 6 Caribou County, ID. Proposed drilling would be located in Caribou County, Idaho; approximately 18 miles Northeast of Soda Springs, ID. | |||||
|
Rasmussen Valley Mine EIS |
- Minerals and Geology |
In Progress: NOI in Federal Register 03/01/2011 Est. DEIS NOA in Federal Register 10/2013 |
Expected:10/2014 |
11/2014 |
Jack Isaacs 208-547-4356 jisaacs@fs.fed.us |
| Description: Nu-West Industries, Inc., submitted a Mine and Reclamation Plan (MRP) which proposes new open-pit phophate mining operations on federal leases I-05975, and some adjacent private lands. It also proposes lease modification and several Special Use Auth
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=37876 |
|||||
| Location: UNIT - Soda Springs Ranger District. STATE - Idaho. COUNTY - Caribou. LEGAL - T. 7 S., R. 44 E., Sections: 4, 5, 6, 8, & 9. T. 6 S., R. 43 E., Sections: 26, 34, 35, & 36. T. 7 S., R. 43 E., Sections: 1. Proposed mining operations would be located in Caribou County, ID; approximately 18 miles Northeast of Soda Springs, ID. | |||||
|
Squaw Creek Watershed Restoration Project EA *NEW LISTING* |
- Recreation management - Watershed management - Road management |
In Progress: Scoping Start 03/04/2012 Est. 215 Comment Period Legal Notice 05/2012 |
Expected:06/2012 |
08/2012 |
Devon Green 208-547-1116 dhgreen@fs.fed.us |
| Description: The purpose of this project is to restore proper hydrological function and improve aquatic habitat within the upper Squaw Creek watershed, and to best provide safe and sustainable recreational access to non-motorized trails #456 and #454.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=38405 |
|||||
| Location: UNIT - Soda Springs Ranger District. STATE - Idaho. COUNTY - Bonneville. LEGAL - T04S R45E Sections 11, 13, 24 and NE ¼ of 14; T04S R46E Section 19. Approximately 6 miles west-northwest of Etna, WY or 37 miles northeast of Soda Springs, ID. Activities are proposed within the Squaw Creek drainage, which is a tributary to Jackknife Creek. | |||||
|
Tincup Mountain Aspen Restoration CE |
- Fuels management |
In Progress: 215 Comment Period Legal Notice 03/21/2008 |
Expected:11/2012 |
09/2013 |
Rebecca Phelps 208-547-1118 roophelps@fs.fed.us |
| Description: Treat a total of 3,000 acres of aspen and sub-alpine with prescribed fire to promote aspen regeneration. Some mechanical treatments may be used to construct fire lines.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=23217 |
|||||
| Location: UNIT - Soda Springs Ranger District. STATE - Idaho. COUNTY - Caribou. LEGAL - T.5S., R.44E., Secs 1, 10 - 15 and T.5S., R.45E., Secs 5 - 9 and 16 - 18. 35 miles North East of Soda Springs; North of Highway 34. | |||||
|
Winschell Dugway ATV Trail System EA |
- Recreation management - Heritage resource management - Watershed management |
Completed |
Actual: 02/17/2012 04/13/2011 |
08/2012 |
Glenn Lackey 208-547-4356 glackey@fs.fed.us |
| Description: Construct and reconstruct 7.8 miles of ATV trail from Caribou City to Morgan Meadows. New construction will connect the historic Dugway with abandoned mining road down the Bilk Creek drainage and into Caribou City. Install 2 bridges across Bilk Ck.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=20098 |
|||||
| Location: UNIT - Soda Springs Ranger District. STATE - Idaho. COUNTY - Bonneville. LEGAL - Range 44 East, Township 4 South sections 2,3,7,9,10,15,18 and 22. South, East and North aspects of Caribou Mountain on the Soda Springs Ranger District, Caribou-Targhee National Forest. | |||||
| Back To Top | |||||
Caribou-Targhee National Forest, Teton Basin Ranger District (excluding Projects occurring in more than one District) |
R4 - Intermountain Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Badger Creek Precommercial Thinning and Aspen Enhancement Project CE |
- Vegetation management (other than forest products) |
In Progress: 215 Comment Period Legal Notice 12/17/2008 |
Expected:03/2012 |
07/2012 |
Mike Alfieri 208-558-7301 malfieri@fs.fed.us |
| Description: Proposing to non-commercially thin dense lodgepole pine stands while emphasizing aspen species composition on approximately 1,400 acres. | |||||
| Location: UNIT - Teton Basin Ranger District. STATE - Idaho, Wyoming. COUNTY - Teton, Teton. LEGAL - T7N R45E, Sections 10, 11, 14, 15, 23-26, and 36. T7N, R46E, Sections 30-32 (State of Idaho). T45N, R118W, Sections 8, 17, 20, 21, 27, 28, 33, 34, and 35 and T45N, R118W, Sec 3 (State of Wyoming). Western front of the Teton Range within the Badger, Leigh and Teton Watersheds, in Teton County, Idaho and Teton County, Wyoming. | |||||
|
Darby Canyon Trailhead Relocation EA |
- Recreation management - Wildlife, Fish, Rare plants |
In Progress: Scoping Start 03/14/2011 Est. 215 Comment Period Legal Notice 01/2012 |
Expected:02/2012 |
07/2012 |
Lee Mabey 208-557-5784 lmabey@fs.fed.us |
| Description: Relocate trailhead .25 miles west to a location away from Darby Creek to protect water quality, fisheries and reduce trailhead congestion. Rehabilitate the road beyond new trailhead and convert to a nonmotorized trail. Replace main trail bridge. | |||||
| Location: UNIT - Teton Basin Ranger District. STATE - Wyoming. COUNTY - Teton. LEGAL - T. 43 N. R 118 W. Sec 14. End of Forest Road 012, Darby Canyon, Southeast of Driggs, Idaho. | |||||
|
Kirkham Hollow Conifer Thinning and Aspen Enhancement Project CE |
- Vegetation management (other than forest products) - Fuels management |
On Hold | N/A | N/A |
Dave Ovard 208-354-6616 dovard@fs.fed.us |
| Description: Enhance aspen on 125 acres. Patches/clones/groups of aspen dominated by sapling/suckers will be identified and all conifer trees <6.0 inch DBH within their boundary will be cut. Conifer outside the aspen patches will be thinned to 11x11 (360 tr/ac) | |||||
| Location: UNIT - Teton Basin Ranger District. STATE - Idaho. COUNTY - Madison. LEGAL - T5N, R43E, Sections 30 and 31. West of Driggs, ID on Forest Road 816, a closed road originating on FR 328 (Kirkham Hollow) which is accessed via State Highway 33. | |||||
|
Papoose and Sheep Bridge Trails EA |
- Recreation management - Watershed management |
In Progress: Scoping Start 03/14/2011 Est. 215 Comment Period Legal Notice 01/2012 |
Expected:02/2012 |
06/2012 |
Kurt Kluegel 208-354-6615 kkluegel@fs.fed.us |
| Description: Manage the user-created Papoose and Sheep Bridge Trails as system, nonmotorized trails. Repair the Sheep Bridge and construct a new trail bridge near Reunion Flat Campground. Rehab and close dispersed camping areas near the Sheep Bridge.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=35697 |
|||||
| Location: UNIT - Teton Basin Ranger District. STATE - Wyoming. COUNTY - Teton. LEGAL - T44N,R118W, Sections 13,22,23 and 24, Boise Meridian. East of Driggs, Idaho on Teton Creek Road (FR 009), South of the winter parking area. | |||||
|
Upper Horseshoe Creek Aspen Protection CE |
- Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management |
Developing Proposal Est. Scoping Start 01/2012 |
Expected:02/2012 | 08/2012 |
Dave Ovard 208-354-6616 dovard@fs.fed.us |
| Description: Remove seral conifer from healthy aspen clumps to enhance and regenerate aspen on approximately 50 acres. Confier <5 inches in diameter would be cut while the larger confier would be ringed, or girdled, to kill the tree. | |||||
| Location: UNIT - Teton Basin Ranger District. STATE - Idaho. COUNTY - Teton. LEGAL - T5N, R44E, Section 29; T5N, R43E, Section 24. Approximately 11 miles west of Driggs, Idaho; within 500 feet of Forest Road 235, on the upper two miles of Horseshoe Creek. | |||||
| Back To Top | |||||
Caribou-Targhee National Forest, Westside Ranger District (excluding Projects occurring in more than one District) |
R4 - Intermountain Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Bannock Guard Station Watershed Improvement Project CE |
- Wildlife, Fish, Rare plants - Watershed management |
In Progress: Scoping Start 02/16/2011 |
Expected:04/2012 |
08/2012 |
Brad Higginson 208-557-5786 bhigginson@fs.fed.us |
| Description: The proposed action is to restore approximately 1,000 feet of Mink Creek in the Bannock Guard Station (GS) area, upsize the bridge on the Guard Station access road, modify the culvert bone-yard, and stabilize streambanks at the Mink Creek Group Site.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=35550 |
|||||
| Location: UNIT - Westside Ranger District. STATE - Idaho. COUNTY - Bannock. LEGAL - T8S; R35E; Section 18 NW ¼. 9 1/2 miles south of Pocatello, ID along Mink Creek through the Guard Station and Mink Creek Group Site. | |||||
|
Bird Canyon Fuels Reduction Project CE |
- Fuels management |
In Progress: Scoping Start 02/27/2012 Est. 215 Comment Period Legal Notice 08/2012 |
Expected:12/2012 |
05/2013 |
Arik Jorgensen 208-236-7540 ajorgensen@fs.fed.us |
| Description: To modify and improve vegetation conditions to increase the probability of success for managing wildfires adjacent to private homes and improvements. Therefore, we will create strategic fuel breaks and promote aspen, to limit fire spread.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=37533 |
|||||
| Location: UNIT - Westside Ranger District. STATE - Idaho. COUNTY - Bannock. LEGAL - T9S R38E, Sections:5-8; T8S R38E, Sections:29-32; T8S R37E Sections: 24-26. Approximately 4 miles north of Lava Hot Springs, ID. | |||||
|
Pocatello, Michaud, and Midnight Cattle Grazing Reauthorization EIS |
- Grazing management |
Developing Proposal Est. NOI in Federal Register 04/2012 |
Expected:02/2013 | 06/2013 |
Heidi Heyrend 208-557-5791 hheyrend@fs.fed.us |
| Description: Reauthorize grazing on the Pocatello, Michaud, and Midnight Cattle allotments. Project currently on-hold to collect and analyze more field data.
Web Link: http://www.fs.fed.us/nepa/nepa_project_exp.php?project=33644 |
|||||
| Location: UNIT - Westside Ranger District. STATE - Idaho. COUNTY - Bannock, Power. LEGAL - Portions of T7S, R34E; T8S, R34E; T9S, R34E; T8S, R35E; T9S, R35E. These allotments are in the Lower Portneuf watershed south and west of Pocatello. | |||||
|
South Mink Prescribed Fire CE |
- Vegetation management (other than forest products) - Fuels management |
On Hold | N/A | N/A |
Arik Jorgensen 208-236-7540 ajorgensen@fs.fed.us |
| Description: Use prescribed fire to reduce hazardous fuel accumulations, regenerate brush communities, increase the amount of young aspen and reduce conifer encroachment across the project area. No road construction or reconstruction will be necessary. | |||||
| Location: UNIT - Westside Ranger District. STATE - Idaho. COUNTY - Bannock. LEGAL - T9S, R35E, Sections 4, 5, 6, 7, 8, 9 and a portion of T9S, R34E, Section 1. 15 Miles South of Pocatello Idaho. | |||||
|
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or part of an individual's income is derived from any public assistance program. (Not all prohibited bases apply to all programs.)
Persons with disabilities who require alternative means for communication of program information (Braille, large print, audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice and TDD). To file a complaint of discrimination, write USDA, Director, Office of Civil Rights, 1400 Independence Avenue, SW, Washington, DC 20250-9410 or call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity provider and employer. This report contains the best available information at the time of publication. Questions may be directed to the Project Contact. |
|||||