Schedule of Proposed Actions (SOPA) |
|||||
| This report contains the best available information at the time of publication. Questions may be directed to the Project Contact. | |||||
|
Report Contents (click to jump to a section) : - Projects Occurring Nationwide - R3 - Southwestern Region, Occurring in more than one Forest (excluding Regionwide) - R3 - Southwestern Region, Kaibab National Forest, Forestwide (excluding Projects occurring in more than one Forest) - R3 - Southwestern Region, Kaibab National Forest, North Kaibab Ranger District (excluding Projects occurring in more than one District) - R3 - Southwestern Region, Kaibab National Forest, Tusayan Ranger District (excluding Projects occurring in more than one District) - R3 - Southwestern Region, Kaibab National Forest, Williams Ranger District (excluding Projects occurring in more than one District) | |||||
Projects Occurring Nationwide |
|||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|---|---|---|---|---|---|
|
Gypsy Moth Management in the United States: A Cooperative Approach EIS |
- Vegetation management (other than forest products) |
In Progress: DEIS NOA in Federal Register 09/19/2008 Est. FEIS NOA in Federal Register 12/2011 |
Expected:01/2012 |
01/2012 |
Noel Schneeberger 610-557-4121 nschneeberger@fs.fed.us |
| Description: The USDA Forest Service and Animal and Plant Health Inspection Service are analyzing a range of strategies for controlling gypsy moth damage to forests and trees in the United States.
Web Link: http://www.na.fs.fed.us/wv/eis/ |
|||||
| Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. Nationwide. | |||||
|
Land Management Planning Rule EIS |
- Regulations, Directives, Orders |
In Progress: DEIS NOA in Federal Register 02/25/2011 Est. FEIS NOA in Federal Register 11/2011 |
Expected:12/2011 |
12/2011 |
Larry Hayden 202-205-1559 lhayden@fs.fed.us |
| Description: The Department of Agriculture proposes to promulgate a new planning rule, which will set out the process for development, revision, and amendment of National Forest System land management plans.
Web Link: http://www.fs.usda.gov/planningrule |
|||||
| Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. Agency-wide Rule. | |||||
|
Nationwide Aerial Application of Fire Retardant on National Forest System Lands. EIS |
- Regulations, Directives, Orders |
In Progress: NOI in Federal Register 08/27/2010 Est. DEIS NOA in Federal Register 05/2011 |
Expected:12/2011 |
01/2012 |
Glen Stein 208-869-5405 gstein@fs.fed.us |
| Description: The Forest Service will prepare a programmatic environmental impact statement for the continued nationwide aerial application of fire retardant on National Forest System lands.
Web Link: http://www.fs.fed.us/fire/retardant/index.html |
|||||
| Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. Nationwide. | |||||
| Back To Top | |||||
R3 - Southwestern Region, Occurring in more than one Forest (excluding Regionwide) |
|||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Exploratory Core Drilling - Coconino and Kaibab Material Site Investigations CE |
- Minerals and Geology | Completed | Actual: 07/07/2011 | 07/2011 |
Mike Dechter 928-527-3416 mdechter@fs.fed.us |
| Description: Drilling of 6-8 inch diameter holes at 5 locations to determine the geologic make-up of the site for potential use as a rock pit. Includes using a truck-mounted auger to drill one or possibly two holes per location, then backfilling the excavation.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=35646 |
|||||
| Location: UNIT - Williams Ranger District, Tusayan Ranger District, Peaks Ranger District, Mogollon Rim Ranger District. STATE - Arizona. COUNTY - Coconino. See map of 5 drilling locations. | |||||
|
Four-Forest Restoration Initiative EIS: Kaibab and Coconino EIS |
- Forest products - Vegetation management (other than forest products) - Fuels management - Watershed management - Road management |
In Progress: NOI in Federal Register 08/19/2011 Est. DEIS NOA in Federal Register 01/2012 |
Expected:10/2012 |
01/2013 |
Paula Cote 928-226-4686 pcote@fs.fed.us |
| Description: Implementation of forest restoration activities including thinning of trees, prescribed fire treatments, and watershed and road restoration within 988,764 acres of the Coconino and Kaibab national forests.
Web Link: http://www.fs.usda.gov/4fri |
|||||
| Location: UNIT - Williams Ranger District, Tusayan Ranger District, Peaks Ranger District, Mormon Lake Ranger District, Mogollon Rim Ranger District. STATE - Arizona. COUNTY - Coconino, Yavapai. All ponderosa pine habitat on the Kaibab and Coconino National Forests. | |||||
|
Rock Pit Development: Coconino and Kaibab National Forests EA |
- Road management |
In Progress: Scoping Start 04/06/2011 Est. 215 Comment Period Legal Notice 10/2011 |
Expected:01/2012 |
05/2012 |
Mike Dechter 928-527-3416 mdechter@fs.fed.us |
| Description: Development of up to 39 rock pits affecting a total of 434 acres on the Coconino and Kaibab national forests to provide materials for surfacing roads to maintain safe and sustainable road conditions.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=34858 |
|||||
| Location: UNIT - Williams Ranger District, Tusayan Ranger District, Coconino National Forest All Units. STATE - Arizona. COUNTY - Coconino, Yavapai. locations throughout the Coconino and Kaibab national forests (see map). | |||||
| Back To Top | |||||
Kaibab National Forest, Forestwide (excluding Projects occurring in more than one Forest) |
R3 - Southwestern Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Kaibab National Forest Plan Revision EIS |
- Land management planning |
In Progress: NOI in Federal Register 04/23/2010 Est. DEIS NOA in Federal Register 12/2011 |
Expected:09/2012 |
11/2012 |
Ariel Leonard 928-635-8283 aleonard@fs.fed.us |
| Description: Revise the Kaibab National Forest's Land and Resource Management Plan
Web Link: http://fs.usda.gov/goto/kaibab/plan_revision |
|||||
| Location: UNIT - Kaibab National Forest All Units. STATE - Arizona. COUNTY - Coconino, Mohave, Yavapai. LEGAL - T 19N - 25N, R 2W - 5E; T 27N - 32N, R 1W - 6E; and T34N - 40N, R 4W - 5E, lands within the Kaibab National Forest Boundary. Kaibab National Forest Lands surrounding the City of Williams and bordering Grand Canyon National Park to the north and south. | |||||
| Back To Top | |||||
Kaibab National Forest, North Kaibab Ranger District (excluding Projects occurring in more than one District) |
R3 - Southwestern Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Cancoop Vegetation Management & Wildlife Habitat Improvement Project CE |
- Recreation management - Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management |
On Hold | N/A | N/A |
Edward Hiatt 928-643-8101 erhiatt@fs.fed.us |
| Description: Prescribed burning on approximately 6230 acres to improve timber stand and vegetative structure.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=35851 |
|||||
| Location: UNIT - North Kaibab Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - T40N, R2E, Sections 22, 23, 24, 25, 26, 27, 28, 33, 34, 35, 36, and T39N, R2E, Sections 1, 2, 3, 4, 11, 12, G&SRBM. Project is located along the north central portion of the Kaibab Plateau within the North Kaibab Ranger District. | |||||
|
Goshawk Demonstration Plot(s) CE |
- Wildlife, Fish, Rare plants - Forest products - Vegetation management (other than forest products) - Fuels management - Research and Development |
Developing Proposal Est. Scoping Start 10/2011 |
Expected:11/2011 | 11/2011 |
Paul Callaway 928-643-8150 pcallaway@fs.fed.us |
| Description: Demonstration Plot(s) on approximately 65 acres to improve timber stand and vegetative structure for wildlife habitat, within the ponderosa pine forest.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=35854 |
|||||
| Location: UNIT - North Kaibab Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - T36N, R1E, G&SRBM. 65 acres within the Southwest-to-Central portion of the Kaibab Plateau within the North Kaibab Ranger District. | |||||
|
Horse Springs Trail Re-route CE |
- Recreation management | Completed | Actual: 08/29/2011 | 10/2011 |
David Sanders 928-643-8163 davidsanders@fs.fed.us |
| Description: Re-route portions of the Horse Spring Trail to improve location. Constructing, repairing or reconstructing sections of Horse Springs Trail number 124 will increase safety for hikers, equine, and pack stock, while providing a sustainable solution.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=34645 |
|||||
| Location: UNIT - North Kaibab Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - T38N, R3W, Section 36 and T37N, R3W, Section 1, G&SRBM. North Kaibab Ranger District. | |||||
|
Jacob-Ryan Vegetation Management Project EA |
- Land management planning - Vegetation management (other than forest products) - Fuels management |
In Progress: 215 Comment Period Legal Notice 06/20/2011 |
Expected:10/2011 |
12/2011 |
David Vincelette 928-643-8143 djvincelette@fs.fed.us |
| Description: The JR Vegetation Mgt. Project is located in the North central portion of North Kaibab Ranger District. Forest Restoration that facilitates forest ecosystem sustainability by changing the structure of even-aged stands toward uneven-aged.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=32654 |
|||||
| Location: UNIT - North Kaibab Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - T 38, 39, 40N; R 1, 2, 3E and R1W. north central portion of the North Kaibab Ranger District. | |||||
|
Kane Ranch Allotment Management Environmental Assessment EA *NEW LISTING* |
- Grazing management |
Developing Proposal Est. Scoping Start 12/2011 |
Expected:06/2013 | 08/2013 |
Dustin Burger 928-643-8136 dburger@fs.fed.us |
| Description: Forest Service project to re-evaluate and re-align the Allotment Management Plan for Kane Ranch operations on the Kaibab National Forest to address changes in vegetative conditions and provide adaptive, flexible grazing rotations for 10 to 20 years.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=37319 |
|||||
| Location: UNIT - North Kaibab Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - Townships 34 -38 North, Ranges 1 - 3 West and 1 - 4 East, Gila & Salt River Baseline & Merdian; (Coconino County, AZ). Approximately 480,000 acres located on Kaibab National Forest - North Kaibab Ranger District, which includes Central Summer, Central Winter, Kane and Kanab Creek allotments. | |||||
|
Moquitch Wildlife Habitat Improvement Project CE |
- Land management planning - Vegetation management (other than forest products) - Fuels management |
Completed | Actual: 08/31/2011 | 09/2011 |
Edward Hiatt 928-643-8101 erhiatt@fs.fed.us |
| Description: Thinning of small diameter tree < 12.0" DBH on 500 acres, followed by prescribed burning on approximately 9,500 acres, to improve vegetative structure for wildlife habitat. Treat up to 5,000 acres a year, dependent on weather conditions and budget.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=34642 |
|||||
| Location: UNIT - North Kaibab Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - T 38 N, R 1 E, Sections 24-27, & 34-36; and T 38 N, R 2 E, Sections 19, & 30-31; and T 37 N, R 1 E, Sections 1-3, 10-14, & 23-24; and T 37 N, R 2 E, Sections 6-8, & 17-20,of the Gila & Salt River B&M. North Kaibab Ranger District. | |||||
|
Nankoweap Trail Closure CE |
- Recreation management |
Developing Proposal Est. Scoping Start 08/2011 |
Expected:09/2011 | 09/2011 |
Chelsea McKinney 928-643-8121 cmmckinney@fs.fed.us |
| Description: Closure of up-to four (4) miles of existing, low-usage trail within the Saddle Mountain Wilderness Area.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=35845 |
|||||
| Location: UNIT - North Kaibab Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - T34N, R4E, Sections 15, 22, 27, 28, 32, and 33, G&SRBM. Southeast corner of North Kaibab Ranger District. | |||||
|
North Kaibab Travel Management Project EA |
- Road management |
In Progress: 215 Comment Period Legal Notice 04/25/2011 |
Expected:08/2011 |
09/2011 |
Kevin Larkin 928-643-8135 klarkin@fs.fed.us |
| Description: Identify and establish a motorized road system on the North Kaibab Ranger District and publish a motorized vehicle use map
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=26212 |
|||||
| Location: UNIT - North Kaibab Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - Townships 34 North through 40 North, Ranges 1 East through 5 East and 1 West through 3 West. North Kaibab Ranger District, Kaibab National Forest. | |||||
|
Plateau Facility Fire Protection Project EA |
- Fuels management |
In Progress: Scoping Start 07/22/2010 Est. 215 Comment Period Legal Notice 08/2011 |
Expected:09/2011 |
11/2011 |
David Robinson 928-643-8138 dsrobinson@fs.fed.us |
| Description: Fuels reduction project at multiple sites on the North Kaibab Plateau
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=26210 |
|||||
| Location: UNIT - North Kaibab Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - Townships 34 North through 40 North, Ranges 1East through 5 East and 1 West through 3 West. North Kaibab Ranger District, Kaibab National Forest. | |||||
|
Rainbow Rim Extension CE |
- Recreation management |
In Progress: Scoping Start 07/20/2011 |
Expected:10/2011 |
10/2011 |
Chelsea McKinney 928-643-8121 cmmckinney@fs.fed.us |
| Description: Conversion of up-to seven (7) miles of unimproved road (i.e., old unused timber road) to a hiking and biking trail.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=35820 |
|||||
| Location: UNIT - North Kaibab Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - T34N, R1W, Section 1, and T35N, R1E, Sections 25, 26, 27, 31, 32, 33, 34, 35, and T35N, R1W, Section 36, G&SRBM. Southwest corner of North Kaibab Ranger District. | |||||
| Back To Top | |||||
Kaibab National Forest, Tusayan Ranger District (excluding Projects occurring in more than one District) |
R3 - Southwestern Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Highway 64/180 Wireless Communication Sites Project EA |
- Special use management |
In Progress: 215 Comment Period Legal Notice 07/25/2011 |
Expected:06/2011 |
11/2011 |
John Brown (928) 635-8275 jwbrown@fs.fed.us |
| Description: Const. a self-supported tower, up to 150' tall, at the existing Tusayan Comm. Site. Const. a 150' tall tower on the east side of Hwy 64 six miles south of Tusayan in T29N, R2E Section 24. Modify the KNF Forest Plan to designate the two Comm Sites.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=23632 |
|||||
| Location: UNIT - Tusayan Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - Tusayan site is in SW1/4 of SE1/4, Sec 13, T30N, R2E; second site is in T29N R2E Section 24. Tusayan comm. Site is located one mi. north of Tusayan and just south of GCNP. The 2nd site is on east side of Hwy 64/180 6 mi.s south of Tusayan,. | |||||
|
Russell Vegetation Management Project EA |
- Vegetation management (other than forest products) - Fuels management |
Completed | Actual: 08/19/2011 | 10/2011 |
Mark Nabel 928-638-2443 mrnabel@fs.fed.us |
| Description: Non-commercial thinning and burning on appox. 8,000 acres.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=18997 |
|||||
| Location: UNIT - Tusayan Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - T 29 N, R 5 E – Sec’s 7, 17, 18, 19, 20, 21, 28, 29, 30, 31, 32, 33; T 29 N, R 4 E – Sec’s 12, 13, 14, 22, 23, 24, 25, 26, 36; T 28 N, R 5 E – Sec’s 4, 5, 6. Approximately 15 miles southeast of the town of Tusayan. The project area lies between the Coconino Rim Road (FS 310), FS road 310RC, FS road 320, FS road 301 and FS road 317. | |||||
|
VANE Minerals Uranium Exploratory Drilling Project EIS |
- Minerals and Geology | On Hold | N/A | N/A |
Thomas Mutz 928-635-5661 tmutz@fs.fed.us |
| Description: The project proposal would conduct exploratory drilling at 24 different sites
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=26440 |
|||||
| Location: UNIT - Tusayan Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - Townships 27, 28, and 29 North; and Ranges 2, 3, and 4 East. Tusayan Ranger District. | |||||
| Back To Top | |||||
Kaibab National Forest, Williams Ranger District (excluding Projects occurring in more than one District) |
R3 - Southwestern Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Aspen Restoration Project CE |
- Vegetation management (other than forest products) |
In Progress: Scoping Start 04/05/2011 |
Expected:05/2011 |
06/2011 |
Roger Joos 928-635-5622 rejoos@fs.fed.us |
| Description: Protect and restore aspen stands by thinning competing conifers and protecting regenerating aspen from ungulate browsing.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=24584 |
|||||
| Location: UNIT - Williams Ranger District. STATE - Arizona. COUNTY - Coconino. Williams Ranger District(11030701). | |||||
|
Authorization for Mineral Exploration Activity at Frenchy Pit CE *NEW LISTING* |
- Minerals and Geology | Completed | Actual: 09/07/2011 | 10/2011 |
Thomas Mutz 928-635-5661 tmutz@fs.fed.us |
| Description: Drake Cement is proposing to remove a bulk sample of up to 10,000 cubic yards of material and drill three exploratory holes up to 300' deep to test the quality and suitability of the deposit for cement making.
Web Link: http://fs.usda.gov/goto/kaibab/projects |
|||||
| Location: UNIT - Williams Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - T22N, R3E, Section 2, and T23N, R3E, Section 35. Frenchy Pit. | |||||
|
Bill Williams Mountain Restoration Project EIS |
- Forest products - Vegetation management (other than forest products) - Fuels management - Watershed management |
In Progress: NOI in Federal Register 04/21/2011 Est. DEIS NOA in Federal Register 07/2011 |
Expected:12/2011 |
04/2012 |
Thomas Mutz 928-635-5661 tmutz@fs.fed.us |
| Description: The purpose of the project is to improve the health and sustainability of forested conditions on and surrounding Bill Williams Mountain by reducing hazardous fuels and moving vegetative conditions in the project area toward desired conditions.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=34690 |
|||||
| Location: UNIT - Williams Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - All or portions of Sections 1-3, 10-15, 22-27, & 34-36 T21N R1E; Sections 4-10, 15-22, & 27-31 T21N R2E; and Sections 31-33 T22N R2E Gila & Salt River Meridian. The project area is located 4 miles south-southwest of the city southwest of Williams, Arizona. It is approximately 18,000 acres and encompasses Bill Williams Mountain. | |||||
|
Irishman Dam Allotment Environmental Assessment EA |
- Grazing management | Completed | Actual: 09/01/2011 | 11/2011 |
Jason Stevens 928-635-5625 jasonstevens@fs.fed.us |
| Description: Allotment analaysis for Irishman Dam Allotment
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=33654 |
|||||
| Location: UNIT - Williams Ranger District. STATE - Arizona. COUNTY - Coconino, Yavapai. West side of Williams Ranger District. | |||||
|
McCracken Project EA |
- Forest products - Fuels management |
In Progress: 215 Comment Period Legal Notice 11/19/2010 |
Expected:04/2011 |
06/2011 |
Mark Herron 928-635-5644 mherron@fs.fed.us |
| Description: Vegetation Management and Fuels Reduction Project
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=18988 |
|||||
| Location: UNIT - Williams Ranger District. STATE - Arizona. COUNTY - Coconino. Williams Ranger District, project area is south of Williams and I-40. | |||||
|
Recreation/Interpretation Trail between Stone and Steel Dams CE |
- Recreation management - Heritage resource management |
Developing Proposal Est. Scoping Start 11/2010 |
Expected:01/2011 | 06/2011 |
Margaret Hangan 928-635-8342 mhangan@fs.fed.us |
| Description: The proposal is to make a connecting trail from Stone Dam parking area to Steel Dam. The trail would be about 0.35 miles in length and would be a standard/terra trail for non-motorized use. There would be one or two interpretation areas with kiosks.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=34040 |
|||||
| Location: UNIT - Williams Ranger District. STATE - Arizona. COUNTY - Coconino. LEGAL - T21N R1W Section 5 Gila and Salt River Meridian. Approximately 4 miles east of Ash Fork, AZ. | |||||
|
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or part of an individual's income is derived from any public assistance program. (Not all prohibited bases apply to all programs.)
Persons with disabilities who require alternative means for communication of program information (Braille, large print, audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice and TDD). To file a complaint of discrimination, write USDA, Director, Office of Civil Rights, 1400 Independence Avenue, SW, Washington, DC 20250-9410 or call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity provider and employer. This report contains the best available information at the time of publication. Questions may be directed to the Project Contact. |
|||||