Report Contents (click to jump to a section) : - Projects Occurring Nationwide - R1 - Northern Region, Occurring in more than one Forest (excluding Regionwide) - R1 - Northern Region, Lolo National Forest, Occurring in more than one District (excluding Forestwide) - R1 - Northern Region, Lolo National Forest, Missoula Ranger District (excluding Projects occurring in more than one District) - R1 - Northern Region, Lolo National Forest, Ninemile Ranger District (excluding Projects occurring in more than one District) - R1 - Northern Region, Lolo National Forest, Plains/Thompson Falls Ranger District (excluding Projects occurring in more than one District) - R1 - Northern Region, Lolo National Forest, Seeley Lake Ranger District (excluding Projects occurring in more than one District) - R1 - Northern Region, Lolo National Forest, Superior Ranger District (excluding Projects occurring in more than one District) | |||||
Projects Occurring Nationwide |
|||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|---|---|---|---|---|---|
|
Land Management Planning Rule EIS |
- Regulations, Directives, Orders |
In Progress: NOI in Federal Register 12/18/2009 Est. DEIS NOA in Federal Register 12/2010 |
Expected:11/2011 |
12/2011 |
Larry Hayden 202-205-1559 lhayden@fs.fed.us |
| Description: The Department of Agriculture proposes to promulgate a new planning rule, which will set out the process for development, revision, and amendment of National Forest System land management plans.
Web Link: http://www.fs.usda.gov/planningrule |
|||||
| Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. Agency-wide Rule. | |||||
|
Nationwide Aerial Application of Fire Retardant on National Forest System Lands. EIS *NEW LISTING* |
- Regulations, Directives, Orders |
In Progress: NOI in Federal Register 08/27/2010 Est. DEIS NOA in Federal Register 01/2011 |
Expected:12/2011 |
01/2012 |
Glen Stein 208-869-5405 gstein@fs.fed.us |
| Description: The Forest Service will prepare a programmatic environmental impact statement for the continued nationwide aerial application of fire retardant on National Forest System lands.
Web Link: http://www.fs.fed.us/fire/retardant/index.html |
|||||
| Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. Nationwide. | |||||
| Back To Top | |||||
R1 - Northern Region, Occurring in more than one Forest (excluding Regionwide) |
|||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Forest Plan Revision, Lolo, Bitterroot and Flathead National Forests EIS |
- Land management planning | On Hold | N/A | N/A |
Beverly Yelczyn 406-363-7151 byelczyn@fs.fed.us |
| Description: Forest Plan Revision
Web Link: http://www.fs.fed.us/r1/wmpz/ |
|||||
| Location: UNIT - Bitterroot National Forest All Units, Flathead National Forest All Units, Lolo National Forest All Units. STATE - Montana. COUNTY - Flathead, Granite, Lake, Mineral, Missoula, Ravalli, Sanders. Western Montana. | |||||
|
Motorized Access Management within the Selkirk and Cabinet-Yaak Grizzly Bear Recovery Zones EIS |
- Land management planning - Wildlife, Fish, Rare plants |
In Progress: DEIS NOA in Federal Register 05/12/2009 Est. FEIS NOA in Federal Register 12/2010 |
Expected:12/2010 |
01/2011 |
Karl Dekome 208-765-7479 kdekome@fs.fed.us |
| Description: Preparation of a Supplemental EIS to amend land and resource management plans for the Idaho Panhandle, Kootenai, and Lolo National Forests to address motorized access management within the Selkirk and Cabinet-Yaak Grizzly Bear Recovery Zones.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=24882 |
|||||
| Location: UNIT - Idaho Panhandle National Forest All Units, Kootenai National Forest All Units, Lolo National Forest All Units. STATE - Idaho, Montana, Washington. COUNTY - Bonner, Boundary, Lincoln, Sanders, Pend Oreille. LEGAL - Northwestern Montana, northern Idaho, and northeastern Washington. Selkirk and Cabinet-Yaak Grizzly Bear Recovery Zones. | |||||
| Back To Top | |||||
Lolo National Forest, Occurring in more than one District (excluding Forestwide) |
R1 - Northern Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
PBR2000 EA |
- Wildlife, Fish, Rare plants - Watershed management - Road management |
In Progress: 215 Comment Period Legal Notice 03/26/2007 |
Expected:01/2011 |
07/2012 |
Barbara Beckes 406-329-3809 bbeckes@fs.fed.us |
| Description: The Lolo Post Burn EIS decision was not upheld in court. This project would issue a new decision to complete restoration activities originally analyzed in the EIS.Timber harvest is not proposed, only road stabilization, storage, and decommissioning
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=22553 |
|||||
| Location: UNIT - Plains/Thompson Falls Ranger District, Superior Ranger District, Ninemile Ranger District. STATE - Montana. COUNTY - Mineral, Missoula, Sanders. LEGAL - Primary the Ninemile and Trout Creek Drainages. Ninemile, Superior, and Plains Ranger Districts on the Lolo National Forest. | |||||
| Back To Top | |||||
Lolo National Forest, Missoula Ranger District (excluding Projects occurring in more than one District) |
R1 - Northern Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
MEC Powerline CE *NEW LISTING* |
- Special use management |
In Progress: Scoping Start 08/24/2010 Est. 215 Comment Period Legal Notice 10/2010 |
Expected:10/2010 |
11/2010 |
Boyd Hartwig 406-329-1024 bchartwig@fs.fed.us |
| Description: Application by Missoula Electric Cooperative to bury 2.25 miles of existing overhead power lines and replace one utility pole on National Forest System Lands near U.S. Highway 12 in the Lolo Creek Drainage.
Web Link: http://www.fs.usda.gov/goto/lolo/projects |
|||||
| Location: UNIT - Missoula Ranger District. STATE - Montana. COUNTY - Missoula. LEGAL - Section 29, T12N, R22W, and Sections 24, 25, 26, and 34, T12N, R23W. 15 miles west of Lolo, Montana on North side of U.S. Highway 12, between Clark Creek and a location 2 miles east of MDT maintenance facility near Martin Creek. | |||||
|
Marshall Woods Restoration Project EA |
- Recreation management - Wildlife, Fish, Rare plants - Forest products - Vegetation management (other than forest products) - Fuels management - Watershed management - Road management |
In Progress: Scoping Start 08/24/2010 Est. 215 Comment Period Legal Notice 03/2011 |
Expected:04/2011 |
06/2012 |
Tami Paulsen 406-329-3731 tpaulsen@fs.fed.us |
| Description: The intent of this project is to restore functioning ecosystems by enhancing natural ecological processes. This area includes excellent opportunities for restoring vegetation and habitat while decreasing the potential for high intensity wildfire.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=31552 |
|||||
| Location: UNIT - Missoula Ranger District. STATE - Montana. COUNTY - Missoula. LEGAL - T13N, R18W, Sec. 4-8, 18,19; T13N, R19W, Sec.1, 2, 11-14, 22-24; T14N, R18W, Sec. 18-20, 2-34; T14N, R19W, Sec. 13, 23-26, 35, 36 PM MT. The 13,000 acre analysis area is approx. 5 mi. NW of Missoula in Missoula Co. and includes Rattlesnake Crk., Woods Gulch, Marshall Crk., and the S portion of the Rattlesnake National Recreation Area. | |||||
|
Montana Snowbowl Ski Area Expansion EIS |
- Special use management |
In Progress: NOI in Federal Register 01/13/2006 Est. DEIS NOA in Federal Register 12/2010 |
Expected:06/2011 |
09/2011 |
Tami Paulsen 406-329-3731 tpaulsen@fs.fed.us |
| Description: Third-party contractor EIS to analyze the proposed ski area expansion for Montana Snowbowl.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=14392 |
|||||
| Location: UNIT - Missoula Ranger District. STATE - Montana. COUNTY - Missoula. LEGAL - sections 27, 28,32, 33,T15N, R19W; and sections 4 and 5 T14N, R19W, PMM. Nine miles north of Missioula, MT. The area directly west of the existing Montana Snowbowl ski area. | |||||
|
Sapphire Crest Trail CE |
- Recreation management |
In Progress: 215 Comment Period Legal Notice 04/16/2010 |
Expected:08/2011 |
09/2012 |
Andy Kulla 406-329-3962 akulla@fs.fed.us |
| Description: Trail construction and reconstruction to connect existing trail segments, creating a 100-mile long non-motorized trail across the Lolo, Bitterroot, and Beaverhead National Forests on the Sapphire Divide.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=32247 |
|||||
| Location: UNIT - Missoula Ranger District. STATE - Montana. COUNTY - Missoula. LEGAL - T12N, R19W, Sections 12,13; T12N, R18W, Sections 18, 19, 20,21,27,28 and 24; T11N, R18W, Sections 3,10,15,22,27,26 and 36 and T10N, R18 W, Section 2. Sapphire Divide. | |||||
|
Spring - Howard TSI/Fuels Reduction CE *NEW LISTING* |
- Vegetation management (other than forest products) - Fuels management |
Cancelled | N/A | N/A |
Allan Fix 406-329-1044 afix@fs.fed.us |
| Description: Project will consist of understory removal in stands with a 14+ inch dbh Ponderosa pine component and precommercial thinning PP and DF regeneration stands. | |||||
| Location: UNIT - Missoula Ranger District. STATE - Montana. COUNTY - Missoula. LEGAL - PMM, MT. T11N, R23W, Sec 6, T12N, R22W, Sec 6 and 18, T12N, R23W, Sec 2,8,10,12,14,16,18,20,22,24,25,26,28,30 and32, T12N,R24W, Sec 13,24and 26. Project will be within the Lolo, Howard and Graves Creek drainages. | |||||
| Back To Top | |||||
Lolo National Forest, Ninemile Ranger District (excluding Projects occurring in more than one District) |
R1 - Northern Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Rennic Stark Project EA |
- Recreation management - Wildlife, Fish, Rare plants - Forest products - Vegetation management (other than forest products) - Fuels management - Watershed management - Road management |
In Progress: 215 Comment Period Legal Notice 03/08/2010 |
Expected:03/2011 |
09/2011 |
Tami Paulsen 406-329-3731 tpaulsen@fs.fed.us |
| Description: Integrated landscape management treatments designed to: improve forest health, reduce hazardous fuels near communities, improve fish and wildlife connectivity, maintain water quality, and provide and maintain forest industry infrastructure.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=31616 |
|||||
| Location: UNIT - Ninemile Ranger District. STATE - Montana. COUNTY - Mineral, Missoula. LEGAL - T14N,R22W,sec5-7;T14N,R23W,sec 1-3,6:T14N,R24W,sec1,2; T15N,R22W,sec7,16,17,19-21,28-32;T15N,R23W,sec1-36;T15N,R24W,sec 1,2,10-13,24;T16N,R23W,sec 20,21,27-35;T16N,R24W sec25,26,34-36PM MT. The 36,000 acre analysis area is west of the Ninemile Ranger Station. It straddles the Ninemile Divide from the Clark Fork River on the southern boundary to Fire Creek on the north. | |||||
|
Rim Rock 1 CE |
- Minerals and Geology | Completed | Actual: 07/13/2010 | 07/2010 |
Victoria Burkhardt 406-626-5402 vburkhardt@fs.fed.us |
| Description: Mining of placer terrace deposits using hand tools. Process excavated material using a trommel. Process water from trommel discharged to a settling pond; solid wastes used to backfill excavations and depressions on site.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=32189 |
|||||
| Location: UNIT - Ninemile Ranger District. STATE - Montana. COUNTY - Mineral. Section 2, T14N, R26W. | |||||
|
Upper Ninemile Placer Mine Reclamation EA |
- Wildlife, Fish, Rare plants - Watershed management - Minerals and Geology |
In Progress: Scoping Start 06/28/2010 Est. 215 Comment Period Legal Notice 05/2011 |
Expected:06/2011 |
06/2012 |
Aubree Benson 406-329-3950 aubreebenson@fs.fed.us |
| Description: Reclamation of abandoned placer mines with restoration of stream channels and fish habitat along Upper Ninemile, Sawpit, Martina, and Twin Creeks.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=32296 |
|||||
| Location: UNIT - Ninemile Ranger District. STATE - Montana. COUNTY - Missoula. LEGAL - Sections 21, 22, 25-27, and 36, T17N, R24W. Various stream segments within the Ninemile Creek Drainage, Ninemile Ranger District, Lolo National Forest. | |||||
|
White Mountain outfitters camp construction CE |
- Recreation management | On Hold | N/A | N/A |
Ryan Domsalla 406-626-5404 rdomsalla@fs.fed.us |
| Description: Replace current "end of road" camp at Cache Cr Trailhead at new location 0.5 mile away in visually screened site off main access road. Work involves 300 feet road construction on old skid trail, clearing 30x30 ft trailer pad, and temporary corral. | |||||
| Location: UNIT - Ninemile Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - NW1/4 Section 8, T12N, R24W, PMM. Gentle bench off Montana Cr Road #4218 approx 1/2 mile before jct with #17442, west of Missoula, MT. | |||||
| Back To Top | |||||
Lolo National Forest, Plains/Thompson Falls Ranger District (excluding Projects occurring in more than one District) |
R1 - Northern Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Antimony EA |
- Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management - Watershed management |
In Progress: Scoping Start 04/06/2010 Est. 215 Comment Period Legal Notice 11/2010 |
Expected:04/2011 |
09/2011 |
John Hamilton 406-826-4345 jehamilton@fs.fed.us |
| Description: Project proposes fuels reduction, forest vegetation management, and wildlife and watershed improvements on about 1000 acres.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=32479 |
|||||
| Location: UNIT - Plains/Thompson Falls Ranger District. STATE - Montana. COUNTY - Sanders. LEGAL - T21N, R32W, Sections 16-21, 28-30,. 13 miles west of Thompson Falls, MT within the Cox Gulch, Antimony Creek and Demont Creek drainages of the Prospect Creek watershed. | |||||
|
City of Thompson Falls Water Facilities Special Use Authorization Renewal CE |
- Special use management |
In Progress: Scoping Start 04/28/2010 |
Expected:11/2010 |
01/2011 |
Ronald Schlader 406-822-3915 rschlader@fs.fed.us |
| Description: 10 year renewal for Special Use permit for the public water system of Thompson Falls located on the Lolo National Forest. Improvements are existing and there will be no ground disturbance for this renewal. | |||||
| Location: UNIT - Plains/Thompson Falls Ranger District. STATE - Montana. COUNTY - Sanders. LEGAL - Water is transported thru buried transmission pipe from point of collection to reservoir through Sections 2 & 3, T21N, R29W, P.M.M. Collection points are located underground in the SW 1/4 of the SW 1/4 of the SE 1/4 of Section 35, T22N, R29W, P.M.M. | |||||
|
Clear Creek EA |
- Recreation management - Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Watershed management |
In Progress: Scoping Start 04/06/2010 Est. 215 Comment Period Legal Notice 06/2011 |
Expected:09/2011 |
07/2012 |
Patricia Partyka 406-826-4314 ppartyka@fs.fed.us |
| Description: Project proposes forest vegetation management, wildlife habitat and watershed improvements, and recreation enhancements within the Clear Creek drainage located about three miles west of Thompson Falls, MT.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=32480 |
|||||
| Location: UNIT - Plains/Thompson Falls Ranger District. STATE - Montana. COUNTY - Sanders. LEGAL - T21N, R30-32W; T22N, R30-32W. Clear Creek drainage within the Prospect watershed about 3 miles west of Thompson Falls, Montana. | |||||
|
Federal Aviation Administration, Special Use Authorization Renewal - Patrick's Knob Comm. Site CE |
- Special use management |
In Progress: Scoping Start 04/28/2010 |
Expected:11/2010 |
01/2011 |
Ronald Schlader 406-822-3915 rschlader@fs.fed.us |
| Description: Special Authorization lease renewal at Patrick's Knob Communication Site located on Lolo National Forest land. Improvements are existing and there will not be any ground disturbing activities associated with this renewal. | |||||
| Location: UNIT - Plains/Thompson Falls Ranger District. STATE - Montana. COUNTY - Sanders. SW 1/4 of Section 25, T19N, R26W, P.M.M. | |||||
|
Haynes Special Use Authorization Renewal-Water Transmission Line CE |
- Special use management |
In Progress: Scoping Start 04/28/2010 |
Expected:11/2010 |
01/2011 |
Ronald Schlader 406-822-3915 rschlader@fs.fed.us |
| Description: Special use renewal for an existing water transmission line, collection tank and impoundment located on Lolo National Forest land. Improvements are existing and there will not be any ground disturbance associated with this renewal. | |||||
| Location: UNIT - Plains/Thompson Falls Ranger District. STATE - Montana. COUNTY - Sanders. NW 1/4 of the SW 1/4 Section , T21N, R28W and the E 1/2 of the NE 1/4 of Section 36, T21N, R29W, P.M.M. | |||||
|
Plains Ranger District Trailhead Improvements CE |
- Recreation management |
In Progress: 215 Comment Period Legal Notice 12/07/2009 |
Expected:12/2010 |
07/2011 |
David Wrobleski 406-826-4321 dwrobleski@fs.fed.us |
| Description: Improve trailheads by increasing turnaround and parking space, and adding gravel surfacing to increase usability of trails to the public. Proposed improvements will make trailheads usable for trailers and 1-3 more vehicles. | |||||
| Location: UNIT - Plains/Thompson Falls Ranger District. STATE - Montana. COUNTY - Sanders. LEGAL - Snowstorm T24N, R26W, Sec 4, Table Top T21N, R30 W, Sec 32, Daisy Crk. T21N, R31W, Sec 25, Evans Gulch T21N, R31W, Sec 30, 24 Mile Crk. T21N, R32W, Sec 13. Trailheads located in the Prospect, Snow Storm and N. end of Thompson River areas. | |||||
|
Plains/Thompson Falls Ranger District Noncommercial Thinning and Pruning Project CE |
- Vegetation management (other than forest products) | Completed | Actual: 08/10/2010 | 06/2011 |
Valerie Walker 406-826-4343 vwalker@fs.fed.us |
| Description: Project would noncommercially thin and prune sapling-sized trees (generally less than 25 feet tall and less than 6 inches in diameter) on approximately 8100 acres in about 277 stands located across the entire Ranger District. | |||||
| Location: UNIT - Plains/Thompson Falls Ranger District. STATE - Montana. COUNTY - Sanders. Plains/Thompson Falls Ranger District. | |||||
|
Sabella Special Use Authorization Renewal-Water Transmission Line CE |
- Special use management |
In Progress: Scoping Start 04/28/2010 |
Expected:11/2010 |
01/2011 |
Ronald Schlader 406-822-3915 rschlader@fs.fed.us |
| Description: Special use permit renewal for an existing buried water transmission line, and a collection tank located on Lolo National Forest land. Improvements are existing and there will be no ground disturbance or changes associated with this renewal. | |||||
| Location: UNIT - Plains/Thompson Falls Ranger District. STATE - Montana. COUNTY - Sanders. NW 1/4 of Sec. 30, T21N, R28W, P.M.M. | |||||
|
Thompson Falls TV District Special Use Authorization Renewal - Clark Mountain #2 Communication Site CE |
- Special use management |
In Progress: Scoping Start 04/28/2010 |
Expected:11/2010 |
01/2011 |
Ronald Schlader 406-822-3915 rschlader@fs.fed.us |
| Description: Renewal of a special use authorization for the Clark Mountain TV Communication Site #2 located on Lolo National Forest land. Improvements are existing and there will not be any ground disturbance associated with this renewal. | |||||
| Location: UNIT - Plains/Thompson Falls Ranger District. STATE - Montana. COUNTY - Sanders. LEGAL - Clark Mountain Communication Site #2. NW 1/4 of the NE 1/4 of Section 33, T21N, R29W, P.M.M. | |||||
|
Turning D Ranch Outfitter/Guide Permit EA |
- Special use management |
In Progress: 215 Comment Period Legal Notice 02/06/2010 |
Expected:08/2011 |
10/2011 |
David Wrobleski 406-826-4321 dwrobleski@fs.fed.us |
| Description: Outfitter/Guide permit application to use the Plains/Thompson Falls Ranger District for a hiking, backpacking, and service activities. | |||||
| Location: UNIT - Plains/Thompson Falls Ranger District. STATE - Montana. COUNTY - Sanders. Plains/Thompson Falls Ranger District. | |||||
| Back To Top | |||||
Lolo National Forest, Seeley Lake Ranger District (excluding Projects occurring in more than one District) |
R1 - Northern Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Big Nelson and Monture Campgrounds Project CE *NEW LISTING* |
- Recreation management - Forest products - Facility management |
In Progress: 215 Comment Period Legal Notice 08/23/2010 |
Expected:11/2010 |
01/2011 |
Tami Paulsen 406-329-3731 tpaulsen@fs.fed.us |
| Description: The proposal is to improve public safety by removing all lodgepole pine >6" dbh within 100' of roads and other improvements. Approx 125 trees in the Big Nelson and 100 in the Monture site will be removed due to bark beetle infestation in the area.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=33463 |
|||||
| Location: UNIT - Seeley Lake Ranger District. STATE - Montana. COUNTY - Powell. LEGAL - Sections 7, 20, and 29 T15N, R10W. Principal Meridian. Big Nelson and Monture Campgrounds. | |||||
|
Colt Summit Restoration/Fuels Project EA |
- Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management - Watershed management |
In Progress: 215 Comment Period Legal Notice 02/06/2010 |
Expected:03/2011 |
09/2011 |
Sandrah Mack 406-375-2638 spmack@fs.fed.us |
| Description: Restoration of forest conditions, fuel reduction and grizzly bear, bull trout, aquatic and riparian habitat on Colt Creek by rerouting Road 646.
Web Link: http://www.fs.usda.gov/goto/lolo/projects |
|||||
| Location: UNIT - Seeley Lake Ranger District. STATE - Montana. COUNTY - Missoula. LEGAL - T18N, R16W, Sect. 2,3,10,11; T19N, R16W, Sect. 23.25-28,33,34, and 36. 10 miles north of Seeley Lake, straddling Highway 83. | |||||
|
Horseshoe West Fuels Reduction and Restoration EA *NEW LISTING* |
- Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management |
In Progress: Scoping Start 07/16/2010 Est. 215 Comment Period Legal Notice 04/2011 |
Expected:05/2011 |
03/2012 |
Julie Knutson 559-920-6646 jcknutson@fs.fed.us |
| Description: Hazardous fuels reduction, vegetation restoration, and wildlife habitat improvement on approximately 3,400 acres near the community of Seeley Lake, Montana.
Web Link: http://www.fs.usda.gov/goto/lolo/projects |
|||||
| Location: UNIT - Seeley Lake Ranger District. STATE - Montana. COUNTY - Missoula. LEGAL - Sections 8, 9, 17-21, and 30, T16N, R14W and Sections 13, 24, and 25, T16N, R15W. Approximately 3 miles southeast of Seeley Lake, Montana near the Double Arrow and Big Sky Lake subdivisions. | |||||
| Back To Top | |||||
Lolo National Forest, Superior Ranger District (excluding Projects occurring in more than one District) |
R1 - Northern Region | ||||
| Project Name | Project Purpose | Planning Status | Decision | Expected Implementation | Project Contact |
|
Amy V Mining Claim Exploration CE *NEW LISTING* |
- Minerals and Geology | Completed | Actual: 09/09/2010 | 10/2010 |
Judy Reese 406-329-3775 jlreese@fs.fed.us |
| Description: Plan of Operation application to dig approximately 20-30 mineral exploration test pits (2x2 foot hole, 4-5 feet deep) in the upper St. Regis basin near Interstate 90. After sample collection, holes will be backfilled and area will be grass-seeded | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - Section 4, T19N, R32W, P.M.M. Upper St. Regis Basin near Interstate 90. | |||||
|
Betts Special Use Authorization Renewal-Private Road Access CE |
- Special use management |
In Progress: Scoping Start 04/28/2010 |
Expected:11/2010 |
01/2011 |
Ronald Schlader 406-822-3915 rschlader@fs.fed.us |
| Description: Special Use permit renewal for year-around access on Road #37337 to private residence. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - T17N; R27W; Section 7; SE1/4 of the SE 1/4 of the SW 1/4; P. M. MT. Approximately 0.75 miles up Keystone Road #389. | |||||
|
Bibler Special Use Authorization Renewal- Water Transmission Line CE |
- Special use management |
In Progress: Scoping Start 04/28/2010 |
Expected:11/2010 |
01/2011 |
Ronald Schlader 406-822-3915 rschlader@fs.fed.us |
| Description: Special Use Permit renewal for an existing domestic and seasonal irrigation water system located on Lolo National Forest land. Improvements are existing and there will not be ground disturbance associated with this renewal. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - South of St. Regis one mile on the South Side Road. T18N, R28W, Section 25, NW 1/4 of the SE 1/4 of the SE 1/4. P.M.M. | |||||
|
Cedar-Thom EIS |
- Recreation management - Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management - Watershed management |
In Progress: NOI in Federal Register 08/07/2009 Est. DEIS NOA in Federal Register 07/2010 |
Expected:03/2011 |
06/2012 |
Patricia Partyka 406-826-4314 ppartyka@fs.fed.us |
| Description: The Cedar-Thom project proposes forest restoration activities, fuels reduction, and recreation enhancements within the Cedar and Thompson Creek drainages, located southwest of Superior, Montana.
Web Link: http://www.fs.fed.us/r1/lolo/projects/ |
|||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - T15N, R28W; T15N, R27W; T16N, R28W; T16N, R27W; T16N, R26W; T17N, R27W. Cedar and Thompson Creek drainages, located southwest of Superior, Montana. | |||||
|
Dry Joe Ecosystem Maintenance Burning CE |
- Wildlife, Fish, Rare plants - Vegetation management (other than forest products) - Fuels management |
In Progress: 215 Comment Period Legal Notice 03/24/2010 |
Expected:05/2011 |
09/2011 |
Lorie Cotter 406-822-3916 lcotter@fs.fed.us |
| Description: Prescribed burning of approximately 5900 acres within several drainages located between the towns of St. Regis and Superior, Montana | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - T17N, R28W, Sections 9, 10, 15-17, 20, 21, 24-27 & 34-36; T17N, R27W, Sections 5-8, 17-21, 25-31 & 34-36; T18N, R27W, Sections 26 & 27; T18N, R26W, Sections 27-29, 32, 33; T16N, R28W, Sections 2-4. Several drainages located between the towns of St. Regis and Superior, Montana. | |||||
|
Gildersleeve Mine Lode Exploration CE *NEW LISTING* |
- Minerals and Geology | Completed | Actual: 09/09/2010 | 10/2010 |
Victoria Burkhardt 406-626-5402 vburkhardt@fs.fed.us |
| Description: Plan of Operations request for lode mine exploration to satisfy BLM mining claim assessment near Snowshoe Gulch, a tributary to Cedar Creek. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - Section 29, T15N R29W, P.M.M. Snowshoe Gulch in Cedar Creek. | |||||
|
Gildersleeve Mine Placer Exploration CE *NEW LISTING* |
- Minerals and Geology | Completed | Actual: 09/09/2010 | 10/2010 |
Victoria Burkhardt 406-626-5402 vburkhardt@fs.fed.us |
| Description: Plan of Operations application for placer mine exploration in previously disturbed mining areas of Snowshoe Gulch, a tributary to Cedar Creek. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - Sections 28 and 29, T15N, R29W, P.M.M. Snowshoe Gulch in Cedar Creek. | |||||
|
Haynes Private Property Access Road via Road 16960 CE |
- Special use management |
In Progress: 215 Comment Period Legal Notice 03/30/2009 |
Expected:01/2011 |
02/2011 |
Ronald Schlader 406-822-3915 rschlader@fs.fed.us |
| Description: Travis and Donna Haynes have requested yearlong access to property they own in Sect. 8 & 9, T17N, R26W. Access would be through existing road 16960 which is an "A" closure. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. T17N, R26W, NW1/4 Sect. 9. | |||||
|
Heart Lake Pit Toilet Installation CE *NEW LISTING* |
- Recreation management | Completed | Actual: 08/20/2010 | 08/2010 |
Allen Byrd 406-822-3977 allenbyrd@fs.fed.us |
| Description: Installation of primitive pit toilet at Heart Lake. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - Section 23, T14N, R27W, P.M.M. Heart Lake in the Trout Creek drainage. | |||||
|
Mother Lode Mine Exploration CE |
- Minerals and Geology | Completed | Actual: 07/26/2010 | 08/2010 |
Victoria Burkhardt 406-626-5402 vburkhardt@fs.fed.us |
| Description: Mine claimants proposed to open four existing mine adits to sample underground for mineralization. Metal portals would be installed using heavy equipment. A brushed-in, non-system road would be cleared just enough to allow for mine access. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - Sections 4 & 5, T17N, R29W. Approximately 10 miles west of St. Regis, above Coyle Creek in the Two Mile Creek drainage. | |||||
|
Mullan Gulch Buried Power Line CE *NEW LISTING* |
- Special use management |
In Progress: 215 Comment Period Legal Notice 08/19/2010 |
Expected:10/2010 |
10/2010 |
Patrick Corts 406-329-3860 pcorts@fs.fed.us |
| Description: NorthWestern Energy proposes to connect to an existing buried powerline that runs along the north side of the Camels Hump road and bury a 780 foot lateral line to private property on the southside of the road. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. T18N, R28W, Sections 8 and 9. | |||||
|
Nelson Special Use Authorization Renewal-Water Transmission Line CE |
- Special use management |
In Progress: Scoping Start 04/28/2010 |
Expected:11/2010 |
01/2011 |
Ronald Schlader 406-822-3915 rschlader@fs.fed.us |
| Description: Special use permit renewal for an existing collection tank and buried waterline located on Lolo National Forest land. Improvements are existing and there will not be any ground disturbing activities associated with this renewal. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. T18N, R28W, Section 25, NE1/4 of the SE 1/4 of the SE 1/4, P.M.M. | |||||
|
Neu Special Use Authorization Renewal-Water Transmission Line CE |
- Special use management |
In Progress: Scoping Start 04/28/2010 |
Expected:11/2010 |
01/2011 |
Ronald Schlader 406-822-3915 rschlader@fs.fed.us |
| Description: Special use permit renewal for an existing water transmission line and storage tank located on Lolo National Forest land. Improvements are existing and there will not be any ground disturbing activities associated with this renewal. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. N 1/2 of Section 17, T16N, R26W, P.M.M. | |||||
|
Route of the Olympian Recreation Project EA |
- Recreation management |
In Progress: Scoping Start 04/15/2010 Est. 215 Comment Period Legal Notice 11/2010 |
Expected:01/2011 |
07/2011 |
Elizabeth Kennedy 406-822-3954 ekennedy@fs.fed.us |
| Description: Designation of the travel management status of approximately 30 miles of abandoned railroad grades (Milwaukee and Northern Pacific) for recreation use between Taft and St. Regis, Montana.
Web Link: http://www.fs.fed.us/nepa/project_content.php?project=32498 |
|||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. The Milwaukee and Northern Pacific abandoned railroad grades between Taft and Saltese, Montana. | |||||
|
Storm Peak Trailhead Relocation CE |
- Recreation management | Completed | Actual: 07/09/2010 | 09/2010 |
Allen Byrd 406-822-3977 allenbyrd@fs.fed.us |
| Description: Relocation of trailhead for Storm Peak Trail #255 to provide better parking and access to the trail. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - NE1/4, Section 27, T19N, R30W, P.M.M. Big Creek drainage south of Haugan, Montana and Interstate 90. | |||||
|
Summer Trails Motorized Management EA |
- Road management |
In Progress: 215 Comment Period Legal Notice 05/12/2009 |
Expected:06/2011 |
08/2011 |
Allen Byrd 406-822-3977 allenbyrd@fs.fed.us |
| Description: Project proposes to establish an ecologically sustainable ATV route system and restore areas damaged by unauthorized motorized use.
Web Link: http://www.fs.fed.us/r1/lolo/projects/index-summer-trails.shtml |
|||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - T17 - 19N, R28 - 32W. West end of the Superior Ranger District from Twomile Creek to Lookout Pass Ski Area. | |||||
|
Tricon Deer Creek Road CE |
- Special use management | On Hold | N/A | N/A |
Ronald Schlader 406-822-3915 rschlader@fs.fed.us |
| Description: Tricon Timber is requesting access to a 40 acre parcel they own (near Haugan MT) in T19N, R29W, Sect. 31 requiring construction of approx 3100' of new rd. across FS lands. Rd would begin on UpUP Rd #4207 and follow trail 250 to the parcel. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - T18N, R30W, Sect 1, NE1/4 and T18N, R29W Sect 6, NW1/4, NW1/4. T18N, R30W, Sect 1, NE1/4 and T18N, R29W Sect 6, NW1/4, NW1/4. | |||||
|
Trout Creek Large Woody Debris project CE *NEW LISTING* |
- Wildlife, Fish, Rare plants | Completed | Actual: 07/26/2010 | 08/2010 |
Jennifer Mickelson 406-826-4350 jmickelson@fs.fed.us |
| Description: Construction of approximately 50 large woody debris jams within about a 5-mile reach of Trout Creek to create fish habitat. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - Sections 23, 26-28, 32-33, T16N, R26W; Sections 5, 7, and 8, T15N, R26W, P.M.M. Mineral County, Montana. The lower 5-mile reach of Trout Creek on National Forest System lands. | |||||
|
Trout Creek Road Riparian Planting Project CE *NEW LISTING* |
- Wildlife, Fish, Rare plants | Completed | Actual: 09/28/2010 | 10/2010 |
Jennifer Mickelson 406-826-4350 jmickelson@fs.fed.us |
| Description: Planting riparian vegetation along the Trout Creek Road (#250) where the road encroaches on the stream. | |||||
| Location: UNIT - Superior Ranger District. STATE - Montana. COUNTY - Mineral. LEGAL - Sections 23, 27-28, 33, T16N, R26W; Sections 5, 7-8, T15N, R26W; Section 24, T15N, R27W, P.M.M. Along Trout Creek Road #250. | |||||
|
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or part of an individual's income is derived from any public assistance program. (Not all prohibited bases apply to all programs.)
Persons with disabilities who require alternative means for communication of program information (Braille, large print, audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice and TDD). To file a complaint of discrimination, write USDA, Director, Office of Civil Rights, 1400 Independence Avenue, SW, Washington, DC 20250-9410 or call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity provider and employer. This report contains the best available information at the time of publication. Questions may be directed to the Project Contact. |
|||||