Schedule of Proposed Actions (SOPA)
10/01/2012 to 12/31/2012
Idaho Panhandle National Forest

This report contains the best available information at the time of publication. Questions may be directed to the Project Contact.
Report Contents (click to jump to a section) :
Projects Occurring Nationwide
R1 - Northern Region, Occurring in more than one Forest (excluding Regionwide)
R1 - Northern Region, Idaho Panhandle National Forest, Forestwide (excluding Projects occurring in more than one Forest)
R1 - Northern Region, Idaho Panhandle National Forest, Occurring in more than one District (excluding Forestwide)
R1 - Northern Region, Idaho Panhandle National Forest,  Bonners Ferry Ranger District (excluding Projects occurring in more than one District)
R1 - Northern Region, Idaho Panhandle National Forest,  Coeur d'Alene Ranger District (excluding Projects occurring in more than one District)
R1 - Northern Region, Idaho Panhandle National Forest,  Priest Lake Ranger District (excluding Projects occurring in more than one District)
R1 - Northern Region, Idaho Panhandle National Forest,  Sandpoint Ranger District (excluding Projects occurring in more than one District)
R1 - Northern Region, Idaho Panhandle National Forest,  St. Joe Ranger DistricT (excluding Projects occurring in more than one District)

Projects Occurring Nationwide  

 
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Gypsy Moth Management in the United States: A Cooperative Approach
EIS
- Vegetation management (other than forest products)  In Progress:
DEIS NOA in Federal Register 09/19/2008
Est. FEIS NOA in Federal Register 09/2012 
Expected:10/2012
 
01/2013 Noel Schneeberger
610-557-4121
nschneeberger@fs.fed.us 
Description: The USDA Forest Service and Animal and Plant Health Inspection Service are analyzing a range of strategies for controlling gypsy moth damage to forests and trees in the United States.
Web Link:  http://www.na.fs.fed.us/wv/eis/
Location: UNIT - All Districts-level Units. STATE - All States. COUNTY - All Counties. Nationwide.
Back To Top

R1 - Northern Region, Occurring in more than one Forest (excluding Regionwide)

 
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Upper Lochsa Land Exchange
EIS
- Land ownership management  In Progress:
DEIS NOA in Federal Register 11/18/2011
Est. FEIS NOA in Federal Register 03/2013 
Expected:03/2013
 
06/2013 Teresa Trulock
208-935-4256
ttrulock@fs.fed.us 
Description: The Forest Service (FS) is considering a land exchange with Western Pacific Timber. The FS would receive approx. 40,000 acres of WPT land in the upper Lochsa River drainage and WPT would recieve an equal value of Forest Service land in north Idaho.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=26227
Location: UNIT - Sandpoint Ranger District, Palouse Ranger District, North Fork Ranger District, Red River Ranger District, Powell Ranger District , Clearwater Ranger District. STATE - Idaho. COUNTY - Benewah, Bonner, Clearwater, Idaho, Kootenai, Latah. The lands to acquire are in the upper Lochsa River drainage on the border of ID and MT. The federal lands to exchange out of are scattered on the Idaho Panhandle, Clearwater, and Nez Perce NF's.
Back To Top

Idaho Panhandle National Forest, Forestwide (excluding Projects occurring in more than one Forest)  

R1 - Northern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
IPNF Noxious Weed Treatment Project
EIS
- Vegetation management (other than forest products)  In Progress:
NOI in Federal Register 10/28/2011
Est. DEIS NOA in Federal Register 11/2012 
Expected:02/2013
 
06/2013 David Cobb
208-443-6854
dcobb@fs.fed.us 
Description: Management of non-native invasive plant species utilizing herbicides, biological control agents, cultural and mechanical methods for weed control.
Location: UNIT - Idaho Panhandle National Forest All Units. STATE - Idaho, Montana, Washington. COUNTY - Benewah, Bonner, Boundary, Clearwater, Kootenai, Latah, Shoshone, Lincoln, Sanders, Pend Oreille. Various locations across the forest.
Idaho Panhandle and Kootenai National Forest, Forest Plan Revision
EIS
- Land management planning  In Progress:
DEIS NOA in Federal Register 01/13/2012
Est. FEIS NOA in Federal Register 01/2013 
Expected:06/2013
 
07/2013 Kent Wellner
208-265-6601 / 208-443-6801
kwellner@fs.fed.us 
Description: Forest Plan Revision
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=894
Location: UNIT - Idaho Panhandle National Forest All Units. STATE - Idaho. COUNTY - Benewah, Bonner, Boundary, Clearwater, Kootenai, Latah, Shoshone. Northern Idaho.
NIC Outfitter Guide Special Use Permit
CE
- Special use management  In Progress:
215 Comment Period Legal Notice 04/24/2012 
Expected:01/2013
 
06/2013 Claire Pitner
208-769-3033
cpitner@fs.fed.us 
Description: North Idaho College (NIC) has requested a temporary Outfitter Guide Special Use Permit to conduct guided activities such as cross-country skiing, avalanche education, kayaking, fly-fishing, hiking, biking and camping on the CDA River RD.
Location: UNIT - Idaho Panhandle National Forest All Units. STATE - Idaho. COUNTY - Benewah, Bonner, Boundary, Kootenai, Shoshone. LEGAL - Multiple across the IPNFs. Specific open system trails, access sites, and dispersed campsites across the Idaho Panhandle National Forests.
Back To Top

Idaho Panhandle National Forest, Occurring in more than one District (excluding Forestwide)  

R1 - Northern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Authorization of Frontier Communication's Existing Telephone and Fiber Optic Lines
CE
- Special use management  Developing Proposal
Est. Scoping Start 04/2013 
Expected:07/2013  08/2013 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Special use authorization
Location: UNIT - Sandpoint Ranger District, Bonners Ferry Ranger District, Priest Lake Ranger District. STATE - Idaho. COUNTY - Bonner, Boundary. Throughout North Idaho: Bonners Ferry, Priest Lake and Sandpoint Ranger Districts.
Selkirk Mountain Range Winter Travel Plan
EIS
- Recreation management  On Hold  N/A  N/A Michael Thom
208-443-6839
mthom@fs.fed.us 
Description: Travel management plan for motorized winter recreation use within the Selkirk Mountain Range on the Bonners Ferry, Priest Lake Ranger District and Sandpoint Ranger District.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=15349
Location: UNIT - Sandpoint Ranger District, Bonners Ferry Ranger District, Priest Lake Ranger District. STATE - Idaho, Washington. COUNTY - Bonner, Boundary, Pend Oreille. Priest Lake, Sandpoint, and Bonners Ferry Ranger Districts.
Back To Top

Idaho Panhandle National Forest,   Bonners Ferry Ranger District (excluding Projects occurring in more than one District)

R1 - Northern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Boundary County Translator - Black Mountain Communication Site Tower Replacement
CE

           *NEW LISTING*
- Special use management  In Progress:
215 Comment Period Legal Notice 08/31/2012 
Expected:01/2013
 
06/2013 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Removal of two existing guyed towers and replacing them with a single 40' self-supporting tower in approximately the same location. Excavation will be limited to leveling the 16' x 16' pad location.
Location: UNIT - Bonners Ferry Ranger District. STATE - Idaho. COUNTY - Boundary. LEGAL - N1/2 of Section 30, T61N, R2E, BM. Black Mountain Communication Site. Map #15.
Boundary County Translator District - Moyie Repeater Site
CE
- Special use management  Completed  Actual: 09/24/2012  08/2012 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Replace current 40' guyed pole and 600 watt windmill with a 30' tower and 1000 watt windmill. Remove eight 25 gallon propane canisters. Repair access trail.
Location: UNIT - Bonners Ferry Ranger District. STATE - Idaho. COUNTY - Boundary. LEGAL - T64N, R2E, section 12, BM. Moyie Repeater Site - access is via Road 2517 Map #4.
Buckhorn
CE

           *NEW LISTING*
- Fuels management  Developing Proposal
Est. Scoping Start 11/2012 
Expected:05/2013  09/2013 Jennifer Anderson
208-267-6758
jlanderson02@fs.fed.us 
Description: Wildlife habitat and big game browse improvement. Also, use prescribed fire to reduce fuels.
Location: UNIT - Bonners Ferry Ranger District. STATE - Idaho, Montana. COUNTY - Bonner, Lincoln. LEGAL - Boise Meridian - T64N, R3E, Sections 15, 16, 20-22, 27-29, 32-34, and T63N, R3E, Sections 3, 4, 9, 10, 15. Principal Meridian - T36N, R34W, Sections 20, 29, 32 and T35N, R34W, Sect. 5, 8, 9, 17. West of Buckhorn Ridge in the Miller, Faro and Keno Creek drainages. The project area is bounded by Deer Creek to the west, Canuck Basin to the north and Buckhorn Ridge to the east. Map #14.
Elk Mountain Farms Water Diversion and Transmission Special Use Permit
CE
- Special use management  In Progress:
Scoping Start 04/01/2010
Est. 215 Comment Period Legal Notice 04/2013 
Expected:07/2013
 
08/2013 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Issue a Special Use Permit for maintenance and use of an existing water system.
Location: UNIT - Bonners Ferry Ranger District. STATE - Idaho. COUNTY - Boundary. LEGAL - Section 22, T64N, R1W, B.M. Fisher Creek drainage. Map #33.
Hall Mission to Drill Exploration Project
CE

           *NEW LISTING*
- Minerals and Geology  Developing Proposal
Est. Scoping Start 10/2012 
Expected:01/2013  05/2013 Kevin Knesek
208-765-7442
ksknesek@fs.fed.us 
Description: Eight sites on existing road prisms used for drill core mineral exploration.
Location: UNIT - Bonners Ferry Ranger District. STATE - Idaho. COUNTY - Boundary. LEGAL - Sections 9, 11, 14 and 18-21, T65N, R1E, B.M. Mission Creek drainage.
Lopez Livestock Area Special Use Permit Renewal
CE
- Special use management  In Progress:
215 Comment Period Legal Notice 06/26/2012 
Expected:10/2012
 
11/2012 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Renewal of an existing Special Use Permit to maintain a livestock area and approximately 450 feet of fence for an additional 10 year period.
Location: UNIT - Bonners Ferry Ranger District. STATE - Idaho. COUNTY - Boundary. LEGAL - SE ¼ SW ¼ of Section 30, T63N, R3E, BM. Map #2. Southwest of Solomon Mountain along Forest Road 435.
Northern Lights Amendment No. 28
CE
- Special use management  Completed  Actual: 08/10/2012  10/2012 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Replace 900' of underground cable with a 3" conduit to feed cable through to the Black Mountain communication site.
Location: UNIT - Bonners Ferry Ranger District. STATE - Idaho. COUNTY - Boundary. LEGAL - T61N, R2E, section 30, BM. Black Mountain. Map #7.
Northern Lights, Inc., Robinson Lake Campground
CE
- Special use management  Developing Proposal
Est. Scoping Start 01/2013 
Expected:04/2013  05/2013 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Replace an underground power line currently under a supplemental use permit (SUP) servicing the Robinson Lake Campground.
Location: UNIT - Bonners Ferry Ranger District. STATE - Idaho. COUNTY - Boundary. LEGAL - T65N, R2E, Section 21, B.M. Robinson Lake Campground. Map #10.
Patchen Access Road Special Use Permit Renewal
CE
- Special use management  Completed  Actual: 07/30/2012  08/2012 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Renewal of an existing Special Use Permit for access across National Forest System lands to access private property for an additional 10 year period. The existing road is approximately 599 feet in length and 20 feet in width (0.28 acres).
Location: UNIT - Bonners Ferry Ranger District. STATE - Idaho. COUNTY - Boundary. LEGAL - NW ¼ of Section 20, T63N, R2E, BM. Map #12. Just north of Dawson Lake.
State of Idaho - Black Mountain Comm Site New Facility
CE

           *NEW LISTING*
- Special use management  Developing Proposal
Est. Scoping Start 10/2012 
Expected:01/2013  05/2013 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Development of a new communication site at the Black Mountain Communication Site. The proposed project includes the installation of a new 24' x 24' communications facility, as well as a 100' self-supporting tower.
Location: UNIT - Bonners Ferry Ranger District. STATE - Idaho. COUNTY - Boundary. LEGAL - N1/2 of Section 30, T61N, R2E, BM. Black Mountain Communications Site, Map #1.
Twenty Mile Creek
EA
- Vegetation management (other than forest products)  In Progress:
Scoping Start 03/02/2012
Est. 215 Comment Period Legal Notice 12/2012 
Expected:02/2013
 
05/2013 Douglas Nishek
208-267-6765
dnishek@fs.fed.us 
Description: Reduce the risk of sediment entering the drinking water through road improvements, road decommissioning, vegetation and fuels management, and to improve grizzly bear habitat.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=37730
Location: UNIT - Bonners Ferry Ranger District. STATE - Idaho. COUNTY - Boundary. LEGAL - T61N, R1E, Sections 25, 26, 35, 36. T61N, R2E, Sections 30, 31. T60N, R1E, Sections 1, 2, 12. T60N, R2E, Sections 6, 7, 18. BM. Twenty Mile Creek and Brown Creek drainages. Map #6.
Back To Top

Idaho Panhandle National Forest,   Coeur d'Alene Ranger District (excluding Projects occurring in more than one District)

R1 - Northern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Avista Burke A & B Transmission Line Reconstruction
CE
- Special use management  Completed  Actual: 07/23/2012  08/2012 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Reconstruction of the existing horizontal transmission pole system (approximately 100 feet wide) into a single 15 feet wide design within the existing right-of-way.
Location: UNIT - Wallace Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - Sections 11 and 12, T48N, R5E; Sections 7, 8 and 9, T48N, R6E, B.M. Along Canyon Creek Rd 7623.
Barney Thin
CE
- Vegetation management (other than forest products)  On Hold  N/A  N/A Lauren Goschke
208-769-3046
lgoschke@fs.fed.us 
Description: Commercially thin to promote western larch on approximately 70 acres, resulting in an estimated 350 mbf of timber volume. Skyline and tractor yarding will be used, requiring 1/2 mile of temporary road construction and 2 miles of road reconstruction.
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Kootenai. LEGAL - Sections 27, 28, 33, 34; T52N, R1W, B.M. Map #4 - Barney Creek drainage north of Walker Saddle.
Declaration Bridge
CE
- Recreation management  On Hold  N/A  N/A Andrew Boggs
208-769-3038
aboggs@fs.fed.us 
Description: Construct a trail bridge across Declaration Creek on Independence Trail 22. The bridge would replace a puncheon that washed out during 1996 flooding.
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T53N, R1E, Section 33, B.M. (Map #8). Independence Trail 22, across Declaration Creek.
Double Placer
CE
- Minerals and Geology  Developing Proposal
Est. Scoping Start 01/2013 
Expected:04/2013  05/2013 Kevin Knesek
208-765-7442
ksknesek@fs.fed.us 
Description: Excavate panel 600' x 30' x 10' and haul pay gravel offsite (private) to process for gold. Gravel returned for reclamation.
Location: UNIT - Wallace Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T49N, R4E, Section 11, B.M. (Map #18). Placer Gulch east of Delta, ID on FR605 in the Trail Creek Drainage.
Elk W Trench
CE
- Minerals and Geology  Developing Proposal
Est. Scoping Start 11/2012 
Expected:07/2013  09/2013 Kevin Knesek
208-765-7442
ksknesek@fs.fed.us 
Description: Brushing existing trenches and access roads, performing geophysical surveys and geochemical surveys.
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Kootenai. LEGAL - T49N, R2W, Sections 7, 8, 17, 18, B.M. (Map #25). Beauty Creek drainage, west of Elk Mountain, near Mineral Ridge.
Fernan Rod & Gun Club Permit Re-Issue
EA
- Special use management  Developing Proposal
Est. Scoping Start 02/2013 
Expected:06/2013  08/2013 Debbie Butler
(208) 443-6822
dabutler@fs.fed.us 
Description: To authorize the continued operation and maintenance of a target range. The target range has operated under the special use permit since 1990. Permit may be issued for up to a 20-year term.
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Kootenai. LEGAL - T50 N, R3W, NE1/4, NW1/4 Section 2, B.M., Map #3. Fernan Hill/Smith Gulch.
Hogback Ridge/Mt. Coeur d'Alene Road Use Permits
CE
- Special use management  Completed  Actual: 07/02/2012  10/2012 Tamara Maiolie
208-769-3071
tmaiolie@fs.fed.us 
Description: Requests from Forest Capital and Stimson Lumber Company to use the Forest Road 378 series to haul logs from their property.
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T48N, R2W, Sections 8, 16-18, and 21; and T49N, R3W, Section 22, B.M. (Map #14). Hogback Ridge and Mt. Coeur d'Alene.
Idaho Fish & Game Trail Creek Facility Authorization
CE
- Special use management  In Progress:
Scoping Start 07/01/2010
Est. 215 Comment Period Legal Notice 10/2012 
Expected:12/2012
 
01/2013 Barbara Hansen
208-769-3050
bjhansen@fs.fed.us 
Description: Occupying facility.
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T52N, R2E, sec. 19, B.M., Map #1. Trail Creek drainage, adjacent to Forest Service Road 422.
Idaho Public Broadcasting System Communication Use Lease Amendment #1
CE
- Special use management  Completed  Actual: 08/13/2012  08/2012 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Idaho Public Broadcasting System proposes to amend their Communication Use Lease to include a generator and 372 gallon diesel fuel tank to provide emergency backup power at their communication facility on West Canfield Butte.
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Kootenai. LEGAL - Section 29, T51N, R3W, B.M. Communication Site on West Canfield Butte, Map #20.
Last Rainbow
CE
- Minerals and Geology  On Hold  N/A  N/A Kevin Knesek
208-765-7442
ksknesek@fs.fed.us 
Description: Excavate ~35 sq. ft. panel to bedrock and dredge inside hole
Location: UNIT - Wallace Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - Sec 11, T49N, R4E, BM. Last Creek in the Trail Creek drainage, along Kings Pass Hwy (#605), Map #16.
Lutherhaven Outfitter Guide Special Use Permit
CE
- Special use management  Completed  Actual: 04/19/2012  07/2012 Claire Pitner
208-769-3033
cpitner@fs.fed.us 
Description: Lutherhaven Ministries has requested a special use permit to allow guided nature hikes, road biking, horseback riding, and other activities on the Coeur d'Alene River R.D.
Location: UNIT - Wallace Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - Multiple across the District. Specific open system trails, access sites, and dispersed camp sites across the Coeur d'Alene River R.D.
Medimont Bank Stabilization Project
CE
- Recreation management
- Watershed management 
Completed  Actual: 06/26/2012  10/2012 Claire Pitner
208-769-3033
cpitner@fs.fed.us 
Description: Stabilize areas of river bank erosion to protect investments at the Medimont Boat Launch, and reduce exposure to heavy metal contamination in the area.
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Kootenai. LEGAL - NW 1/2 of Section 28, T48N, R2W, B.M. Map #24 - Chain Lakes Area of the Coeur d'Alene River Ranger District.
Moon Digs
CE
- Minerals and Geology  Developing Proposal
Est. Scoping Start 11/2012 
Expected:02/2013  05/2013 Kevin Knesek
208-765-7442
ksknesek@fs.fed.us 
Description: Underground mineral exploration involving hand drilling, sampling, and mapping existing adits.
Location: UNIT - Wallace Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T49N, R3E, Section 26, B.M. (Map #23). W. F. Moon Gulch north of Osburn, ID on County Road #930.
NIC Yurt Special Use Permit
CE
- Special use management  On Hold  N/A  N/A Claire Pitner
208-769-3033
cpitner@fs.fed.us 
Description: North Idaho College (NIC) is requesting a Special Use Permit to construct a yurt on West Willow Peak to be used for academic and extracurricular programs, such as avalanche education, natural resource management, etc.
Location: UNIT - Wallace Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T47N, R5E, Section 11, B.M. Near West Willow Peak in the Boulder Creek drainage, Map #9.
Progress Camp Drill Core Exploration
CE
- Minerals and Geology  On Hold  N/A  N/A Kevin Knesek
208-765-7442
ksknesek@fs.fed.us 
Description: Lode mineral exploration consisting of drill holes in five different sites.
Location: UNIT - Wallace Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T50N, R5E, Section 19 and T50N, R4E, Section 10, BM. Map #7 - E. Fk. of Eagle Creek near Oregon Gulch and N. Fk. of the Coeur d'Alene River just upriver from the Shoshone Work Center.
Prospecting Duke
CE
- Minerals and Geology  Developing Proposal
Est. Scoping Start 11/2012 
Expected:02/2013  05/2013 Kevin Knesek
208-765-7442
ksknesek@fs.fed.us 
Description: Trenching 250" x 30' with 200' temporary access road, gravel will be hauled offsite (private) to process for gold and reeturned for reclamation.
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T49N, R4W, Section 4, B.M. Map # 22 - Prospect Gulch south of Babins Junction on the Coeur d'Alene river Ranger District.
Red Beauty HFRA Project
EA
- Vegetation management (other than forest products)
- Fuels management 
Completed  Actual: 08/30/2012  09/2012 Michael Jow
208-769-3070
mjow@fs.fed.us 
Description: Forest stand management, fuel reduction, road construction, road reconstruction and road decommissioning.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=7423
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Kootenai. LEGAL - T48 and 49N, R2 and 3W, B.M. Map #13 - Coeur d'Alene River Ranger District.
Reissuance of Kootenai Electric Cooperative's Authorization
CE
- Special use management  On Hold  N/A  N/A Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Maintenance of electrical rights-of-way
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Kootenai. LEGAL - T48N, R2W, sec. 28; T48N, R4W, sec. 25; T50N, R3W, sec. 3, 4; T51N, R3W, sec. 1, 11, 23; T51N, R4W, sec. 34; T53N, R4W, sec. 27; T54N, R2W, sec. 14, 22, 26, 27, BM. Multiple locations on the District.
Spyglass Lookout Restoration
CE
- Recreation management  Completed  Actual: 07/09/2012  08/2012 Claire Pitner
928-527-3473
cpitner@fs.fed.us 
Description: A multi-year plan to restore Spyglass Lookout groundhouse and association buildings to historic condition.
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T52N, R2E, Section 22, B.M. (Map #15). Spyglass Peak.
Steamboat Aquatic Restoration Project
EA
- Watershed management
- Road management 
On Hold  N/A  N/A John Ruebke
(208) 769-3019
jruebke@fs.fed.us 
Description: Upgrade culverts on open roads, decommission (by removing culvert) on closed roads, reroute segments of encroaching roads, and fish habitat rehabilitation
Location: UNIT - Wallace Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T51N, R2E, Sec 1-6, 8-16, 23 & 24; T51N, R3E, Sec 5-7, 18 & 19; T52N, R1E Sec 24, 25; T52N, R2E, Sec 9, 10, 14-36; T52N, R3E, Sec 30-32, B.M. Map #6 - Steamboat and Scott Creek drainages.
Steamboat Snow Groomer Shed
CE
- Recreation management  In Progress:
215 Comment Period Legal Notice 08/23/2012 
Expected:11/2012
 
08/2013 Andrew Boggs
208-769-3038
aboggs@fs.fed.us 
Description: Construct a storage shed 70x24-foot pole building (wood with metal roof and sides) at Steamboat Trailhead for use by snow groomer. Construction/maintenance would be performed by Shoshone County and its Snowmobile Groomer Board.
Location: UNIT - Wallace Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T50N, R2E, Section 24, B.M. (Map #12). Steamboat Creek Trailhead, at the junciton of Shoshone County Road 1C and Forest Road 400.
Trail 241 Causeway
CE
- Recreation management  In Progress:
Scoping Start 08/01/2012 
Expected:11/2012
 
07/2013 Andrew Boggs
208-769-3038
aboggs@fs.fed.us 
Description: Construct 1,000 feet of causeway through a mud bog area of Marie Creek Trail 241.
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T52N, R2W, Section 15, B.M. (Map #11). One-half mile from the trailhead of Trail 241, along Forest Road 202.
Trails 16, 226 and 113 Redesignation
CE
- Recreation management  In Progress:
Scoping Start 08/23/2012 
Expected:11/2012
 
04/2013 Andrew Boggs
208-769-3038
aboggs@fs.fed.us 
Description: Redesignate Trails 113, 226 and a portion of Trail 16 (from Trail 133 to Trail 226) from "open to motorized vehicles 50 inches or less" to "4WD vehicles greater than 50 inches." No construction or reconstruction would occur.
Location: UNIT - Wallace Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T47N, R2 and 3E, sections 31, 32, 5, 7, 8, 13-17, B.M. (Map #2). St. Joe Divide Trails 226, 113 and the portion of Trail 16 between its junction with Trails 226 and 113.
W&R Land Company LLC Access Road Special Use Permit Renewal
CE
- Special use management  Completed  Actual: 08/23/2012  08/2012 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Renewal of an existing Special Use Permit to provide access across Forest Service System lands for an additional 10 year period. The access road is approximately 0.30 miles and 40 feet in width (1.35 acres).
Location: UNIT - Fernan Ranger District. STATE - Idaho. COUNTY - Kootenai. LEGAL - Township 53 North, Range 2 West, NW ¼ SW ¼ Section 27, BM. Along Forest Road 332, Map #19.
Back To Top

Idaho Panhandle National Forest,   Priest Lake Ranger District (excluding Projects occurring in more than one District)

R1 - Northern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Grandview Resort Permit Reissue
CE
- Special use management  In Progress:
215 Comment Period Legal Notice 05/02/2012 
Expected:10/2012
 
12/2012 Debbie Butler
(208) 443-6822
dabutler@fs.fed.us 
Description: Continue operation and maintenance of one cabin (#11) located on NFSL. The Grandview cabin has operated under permit since 1970. The remainder of the resort is on private property.
Location: UNIT - Priest Lake Ranger District. STATE - Idaho. COUNTY - Bonner. LEGAL - T61N, R4W, Section 20, BM. Reeder Bay area, just NE of the Ledgewood Recreation Residence Tract. Map #29.
Lower Priest
EA
- Forest products  In Progress:
Scoping Start 02/22/2012
Est. 215 Comment Period Legal Notice 10/2012 
Expected:12/2012
 
03/2013 Albert Helgenberg
208-265-6643
ajhelgenberg@fs.fed.us 
Description: Vegetation and fuels management.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=37009
Location: UNIT - Priest Lake Ranger District. STATE - Idaho. COUNTY - Bonner. LEGAL - Portions of T58N, R5W, Sections 11, 12 and 14; T58N, R4W, Sections 6, 7 and 18-21, B.M. Cottonwood Creek, Dubius Creek and Murray Creek drainages accessed by the Gleason-McAbee Falls County Road. Map #3.
Luby Bay Water Association Permit Renewal
CE
- Special use management  In Progress:
215 Comment Period Legal Notice 05/02/2012 
Expected:10/2012
 
12/2012 Debbie Butler
(208) 443-6822
dabutler@fs.fed.us 
Description: Continue authorization for operation and maintenance of an existing community water system that serves 18 recreation residences in the Luby Bay Tract.
Location: UNIT - Priest Lake Ranger District. STATE - Idaho. COUNTY - Bonner. LEGAL - T 60 N, R 5 W, NW 1/4, NE 1/4, Section 24, B.M. Priest Lake, Luby Bay, Map # 23.
Outlet Water Association SUP Amendment
CE
- Special use management  In Progress:
215 Comment Period Legal Notice 06/26/2012 
Expected:10/2012
 
10/2012 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Amend existing Special Use Permit to include a second well, security fencing and improved access to permitted facilities.
Location: UNIT - Priest Lake Ranger District. STATE - Idaho. COUNTY - Bonner. LEGAL - E 1/2, NE 1/4, Section 6, T59N, R4W, B.M. Lamb Creek drainage in the vicinity of Outlet Bay. Map #8.
Priest Lake Museum Association Permit Renewal
CE
- Special use management  In Progress:
215 Comment Period Legal Notice 05/02/2012 
Expected:10/2012
 
12/2012 Debbie Butler
(208) 443-6822
dabutler@fs.fed.us 
Description: 10 year permit renewal. Maintain the artifacts and exhibits at the museum. Provide interpretive services on historical information in the Priest Lake area and provide volunteer staff to provide visitor information services.
Location: UNIT - Priest Lake Ranger District. STATE - Idaho. COUNTY - Bonner. LEGAL - T. 60 N., R. 5 W., NE ¼ Section 24, B.M. Luby Bay, 38 Priest Lake Museum Road. Map #9.
Selkirk Guiding and Outfitting - Trail Ride Ammendment
CE
- Special use management  In Progress:
215 Comment Period Legal Notice 05/08/2012 
Expected:01/2013
 
03/2013 Debbie Butler
(208) 443-6822
dabutler@fs.fed.us 
Description: Guided horseback rides parallel to existing roads near the Priest Lake Ranger District.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=39658
Location: UNIT - Priest Lake Ranger District. STATE - Idaho. COUNTY - Bonner. LEGAL - T61N, R5W, Sections 14, 22, 23, and 15, B.M. Map #5. Nordman, Reeder Creek, and Bismarck Guard Station.
Solo Quartz Crystal Management Area
CE
- Minerals and Geology  On Hold  N/A  N/A Kevin Knesek
208-765-7442
ksknesek@fs.fed.us 
Description: Setting up management parameters for removing crystal material from the site
Location: UNIT - Priest Lake Ranger District. STATE - Washington. COUNTY - Pend Oreille. LEGAL - T34N R45E Section 1, Willamette Meridian. Map #16 - Solo Creek drainage approximately one mile up Road #659.
Back To Top

Idaho Panhandle National Forest,   Sandpoint Ranger District (excluding Projects occurring in more than one District)

R1 - Northern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Bradley Private Road Special Use Permit Renewal
CE

           *NEW LISTING*
- Special use management  In Progress:
215 Comment Period Legal Notice 08/31/2012 
Expected:10/2012
 
11/2012 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Reissuance of a private road special use permit for an additional 20 years.
Location: UNIT - Sandpoint Ranger District. STATE - Idaho. COUNTY - Boundary. LEGAL - NW1/4, SE1/4, NE1/4 of Section 21, T55N, R2W, BM. West from Forest Road 630; Cocolalla. Map #11.
Falling Drill
CE
- Minerals and Geology  Developing Proposal
Est. Scoping Start 11/2012 
Expected:02/2013  06/2013 Kevin Knesek
208-765-7442
ksknesek@fs.fed.us 
Description: Drill core mineral exploration. One drill site is proposed (up to nine holes drilled from one location).
Location: UNIT - Sandpoint Ranger District. STATE - Idaho. COUNTY - Bonner. LEGAL - T.54N., R.1W., Section 1, BM. Falls Creek. Forest Road 1088 to Falls Creek mine site.
Schweitzer Fuels Reduction
CE
- Fuels management  In Progress:
215 Comment Period Legal Notice 03/02/2012 
Expected:11/2012
 
03/2013 Sara Savage
208-443-6834
sesavage@fs.fed.us 
Description: Fuels treatment.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=32709
Location: UNIT - Sandpoint Ranger District. STATE - Idaho. COUNTY - Bonner. LEGAL - Sections 26, 27, and 34, T 58 N, R 2 W, B.M. Sand Creek and Schweitzer Creek, Map # 30.
Back To Top

Idaho Panhandle National Forest,   St. Joe Ranger DistricT (excluding Projects occurring in more than one District)

R1 - Northern Region  
Project Name Project Purpose Planning Status Decision Expected Implementation Project Contact
Avery Water & Sewer District’s Special Use Permit Renewal
CE
- Special use management  Completed  Actual: 08/01/2012  08/2012 Joseph Holzinger
208-765-7279
jholzinger@fs.fed.us 
Description: Renewal of the Avery Water & Sewer District’s Special Use Permit for continued operation and maintenance of an existing sewer line along Forest Highway 50 and the Avery administrative site.
Location: UNIT - Avery Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - Sections 15 and 16, T45N, R5E, B.M. Along Forest Highway 50 and the Avery administrative site.
Lines Creek BPA Electronic Site Expansion
CE
- Special use management  Completed  Actual: 09/11/2012  07/2013 Lynette Myhre
208-245-6034
lmyhre@fs.fed.us 
Description: BPA has requested to upgrade and expand the electronic site used to monitor the Dworshak to Taft transmission line.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=39469
Location: UNIT - Avery Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - SW 1/4, SW 1/4, Section 33, T44N, R2E. Map #8 - Lines Creek in the Bussel Creek drainage.
Marble Creek Splash Dam Fish Passage Project
CE
- Wildlife, Fish, Rare plants  In Progress:
Scoping Start 04/26/2012
Est. 215 Comment Period Legal Notice 11/2012 
Expected:04/2013
 
08/2013 Lisa Hawdon
208-245-6045
lhawdon@fs.fed.us 
Description: The St. Joe Ranger District is partnering with the USFWS, Idaho DEQ, Idaho Dept. of Fish & Game, and Avista Corp to breach two historic splash dams on Marble Creek to increase amount of habitat available for bull trout.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=39210
Location: UNIT - St. Maries Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - Section 1, T43N, R3E, BM. Several miles upstream of the creek's confluence with the St. Joe River within the U.S. Forest Service's Grandmother Mountain Roadless Area.
Quartz Beetle
CE

           *NEW LISTING*
- Vegetation management (other than forest products)  Developing Proposal
Est. Scoping Start 10/2012 
Expected:04/2013  07/2013 Kaysee Miller
208-245-6230
kayseejmiller@fs.fed.us 
Description: The Quartz Beetle project is 19 miles East of Avery in the Quartz Creek drainage of the St Joe River. The Project will consist of commercial thinning on approzimately 65 acres.
Location: UNIT - Avery Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - T45N, R8E, Sec: 14, 15. 19 miles East of Avery in the Quarz Creek area.
Simmons Fuels
CE

           *NEW LISTING*
- Wildlife, Fish, Rare plants
- Vegetation management (other than forest products)
- Fuels management 
In Progress:
Scoping Start 07/13/2012
Est. 215 Comment Period Legal Notice 10/2012 
Expected:05/2013
 
09/2013 Lisa Spinelli
208-245-6025
lspinelli@fs.fed.us 
Description: Rx burning w/ some planting on 8500 acres to facilitate fire mgmt; reduce natural fuels; provide protection to values at risk; enhance conditions for regeneration of whitebark pine, WP & WL; enhance fire resiliency; increase forage for big game.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=39859
Location: UNIT - Avery Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - Multiple sections in T42N, R9E; T43N, R9E; T44N, R9E; T44N, R10E; T44N, R11E. Map #4 - Upper St. Joe River Drainage in Simmons, Washout, Goat, Wampus, Indian, Bonehead, Red Ives, Bedrock, Color, and Game Creeks.
St. Joe Travel Management Plan
EA
- Recreation management
- Road management 
In Progress:
215 Comment Period Legal Notice 09/11/2009 
Expected:02/2013
 
05/2013 Mary Price
208-245-6022
mprice@fs.fed.us 
Description: Designating roads and trails for public motorized vehicle use on the St. Joe Ranger District.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=26188
Location: UNIT - St. Maries Ranger District, Avery Ranger District. STATE - Idaho. COUNTY - Benewah, Clearwater, Latah, Shoshone. St. Joe Ranger District including Avery RD & St. Maries RD.
Windy Larch
CE
- Forest products
- Vegetation management (other than forest products) 
In Progress:
215 Comment Period Legal Notice 12/05/2011 
Expected:10/2012
 
06/2013 Lynette Myhre
208-245-6034
lmyhre@fs.fed.us 
Description: Commercial thinning on approx. 70 acres using skyline and tractor logging systems to improve the health and vigor of the remaining trees, maintain long-lived early-seral tree species, and provide timber products.
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=37600
Location: UNIT - St. Maries Ranger District. STATE - Idaho. COUNTY - Shoshone. LEGAL - Section 5, T42N, R3E, BM. Map #7 - 10 miles NW of Clarkia, ID in the Windy Creek and Gold Center Drainages of the St. Maries River.
Wooden Spur Resource Management Project
EA

           *NEW LISTING*
- Forest products
- Vegetation management (other than forest products)
- Fuels management
- Watershed management 
In Progress:
Scoping Start 07/13/2012
Est. 215 Comment Period Legal Notice 05/2013 
Expected:09/2013
 
06/2014 Timothy Price
208-245-6049
tprice@fs.fed.us 
Description: Vegetation management and water quality improvement in the Cat Spur Drainage on the St. Joe Ranger District
Web Link:  http://data.ecosystem-management.org/nepaweb/nepa_project_exp.php?project=39858
Location: UNIT - St. Maries Ranger District. STATE - Idaho. COUNTY - Clearwater, Shoshone. LEGAL - T41N, R2E, Sections 5 & 6; T42N, R2E, Sections 19-22, 27-30, 31-33. Map #3 - Cat Spur Drainage in the West Fork St. Maries River Drainage on the St. Joe Ranger District.
The U.S. Department of Agriculture (USDA) prohibits discrimination in all its programs and activities on the basis of race, color, national origin, age, disability, and where applicable, sex, marital status, familial status, parental status, religion, sexual orientation, genetic information, political beliefs, reprisal, or because all or part of an individual's income is derived from any public assistance program. (Not all prohibited bases apply to all programs.) Persons with disabilities who require alternative means for communication of program information (Braille, large print, audiotape, etc.) should contact USDA's TARGET Center at (202) 720-2600 (voice and TDD).

To file a complaint of discrimination, write USDA, Director, Office of Civil Rights, 1400 Independence Avenue, SW, Washington, DC 20250-9410 or call (800) 795-3272 (voice) or (202) 720-6382 (TDD). USDA is an equal opportunity provider and employer.

This report contains the best available information at the time of publication. Questions may be directed to the Project Contact.