Panhandle National Forest - Upper

Columbia/Salmon/ Clearwater District BLM

Executive Summary

Dave Brunner, Team Leader

 

 

 

 

During the week of September 10, 1999, an interagency team conducted a field review of the Panhandle NF and the UCSC District-Bureau of Land Management. The purpose of this review was to evaluate compliance with direction in INFISH and the Biological Opinion for Bull Trout. (This area is outside the range of anadromy). Ten projects or issues were field reviewed or discussed. Overall, the field units visited St Joe and Coeur d' Alene Ranger Districts and the Emerald Empire Resource Area have both management and a key staff with a great understanding of the INFISH and BO requirements, and fully support and require the application of this direction to all appropriate activities. There is a close working relationship within the Level I consultation team and an apparent dedication to not only appropriate mitigation and project design, but also to active restoration activities in watersheds.

 

As with many activities, available dollars has inhibited both the implementation of projects and the restoration of watersheds. In some cases, beyond the need for dollars, there is confusion about activities in RHCAs that can be modified to meet RMOs. In other cases, some undesirable results continue because of this confusion (Emerald Creek recreational mining and the livestock grazing in lower Emerald Creek). However, these field units have made great strides toward meeting the requirements and have high potential to be leaders in the protection and restoration of fish habitats as prescribed in INFISH and the Bull Trout BO. Management emphasis is the key to making the required gains and our collective commitment.

 

 


UNITED STATES DEPARTMENT OF THE INTERIOR

BUREAU OF LAND MANAGEMENT

Idaho State Office

1387 South Vinnell Way

Boise, Idaho 83709-1657

 

In Reply Refer To: 6840 (930)                                                              October 26, 1999

 

 

 

Memorandum

 

To:                   Interagency Implementation Team

 

From:               Dave Brunner, Team Lead

 

Subject:            Upper Columbia-Salmon Clearwater BLM District and Panhandle National

                        Forest  INFISH/Bull Trout Biological Opinion Implementation Field Review

 

Attached is a copy of the final review report.  Thanks again to everyone who made it a success.

 

Signed                                                                                                                                                  Authenticated

J. David Brunner                                                                                                           Sharon Olendorff

DSD, Resource Services                                                                                  Staff Assistant (ID930)

 

Attachment

 

cc:

District Manager, BLM UCSC

Supervisor, Panhandle NF

Brett Roper, Panhandle NF

Kathy Stangl, BLM Cottonwood Field Office


 

INFISH/BULL TROUT BIOLOGICAL OPINION (BO) FIELD REVIEW

September 13-17, 1999

Upper Columbia/Salmon Clearwater District

Bureau of Land Management

Panhandle National Forest

U.S. Forest Service

 

Field Review Area

 

St. Joe and Coeur d=Alene Ranger Districts and Emerald Empire Resource Area

 

This is one of four field reviews being conducted in FY 1999.  Other areas include:

Salmon/Challis National Forest and Idaho Falls BLM Resource Area

Lolo National Forest and BLM Garnet Resource Area

Malheur National Forest and BLM Prineville District

 

Field review included discussions and visits to the following projects:

Fernan Heli Timber Sale - FS

Killarney Lake Timber Sale - BLM

St. Joe Sub-basin Integrated Ecosystem Restoration Strategy - Discussion

 

Only - FS

Huckleberry Campground - Discussion Only

Emerald Creek Grazing Allotment - FS

Emerald Creek Recreational Mining Activity - FS

Beauty Bay Campground Stream Restoration - FS

Beauty Bay CERCLA Site/Road Obliteration - FS

Blue Bay Acquisition - BLM

Blue Bay Recreation Site - BLM (Fritz=s Boat Ramp and Office Site)

 

Field Review Team

 

Dave Brunner, BLM Idaho State Office, Team Lead

Cindy Swanson, USFS, Region 1

Jim Caswell, USFS, Clearwater National Forest

Chuck Dunn, USFWS, Portland Regional Office

Ken Troyer, NMFS, Boise Field Office

 

Field Review Objectives

 

To assess how well PACFISH, INFISH, and Biological Opinion requirements are understood and are being applied.

 

To provide a feedback loop to staff, managers, and the Interagency Implementation Team on issues and concerns relative to implementation of PACFISH, INFISH, and the BOs.

 

Acknowledgments

 

The Team wished to thank Brett Roper, Fisheries Biologist on the Panhandle National Forest and Kathy Stangl, Fisheries Biologist for the BLM for their great selection of projects in terms of variety and complexity which led to very meaningful discussions in the field.  We also wish to thank Dave Wright, Forest Supervisor, and Fritz Rennebaum, BLM District Manager for their participation and for having key staff available for participation in our discussions and field visits.

 

Compliments and Kudos

 

1.      Close working relationship of BLM and FS on projects.

 

2.      Good Level I Team relationships between action agency and regulatory agencies.

 

3.      Very good understanding by BLM and FS of the requirements of INFISH and bull trout BO.

 

4.      Great array of projects for review - the good, the bad, and the ugly.

 

5.      Have moved to ecosystem/watershed approach to restoration.

 

6.      Developing priorities and using limited funds where possible to meet priorities.

 

7.      Great support among both the fisheries staff and management.

 

8.      Put a great amount of work into geographic assessment for strategic planning/priority setting.

 

9.      Developed creative ways to use existing project dollars for restoration activities.

 

10.  Taking INFISH one step further to do more than mitigation, i.e., restoration of watersheds (pulling roads).

 

11.  BLM, while not a huge player in watershed restoration, has taken an active role in habitat restoration through key acquisition.

 

12.  The FS and BLM=s willingness to focus the review on difficult issues that required some candid discussion.

 

13.  They are documenting RMO and RHCA modification commensurate with their ability to adjust.


 

14.  Great implementation monitoring on the key projects and a very good sense of the need for some monitoring on other projects (Garnet Mine).

 

15.  Reclamation activity on the Emerald Creek recreational mining was very thoughtful and creative.

 

16.  Beauty Creek is an example of having on-the-ground expertise working with the contractor.

 

17.  Beauty Creek is a great example of trying to restore a creek bed and maintain an existing campground.

 

Comments and Suggestions

 

1.      Improve understanding and involvement or expand the role of Level II Teams (i.e., CERCLA question or communication with non-federal groups).

 

2.      Need clarification of relationship between CERCLA and ESA on need for consultation (both NF and IIT).

 

3.      Need to maintain a higher degree of communication between segments of the organization on road obliteration.

 

                                                                                       i.      Fernan-Heli                  Apply like standards/controls

                                                                                     ii.      Silver-tip Mine  in both situations

 

                                                                                    iii.      Have road obliteration expertise be more closely associated with any activities which require road obliteration.

 

4.      Need to develop/enhance/prioritize long-term effectiveness monitoring for those projects with high degrees of risk in order to learn from or substantiate improvement.  Stay abreast of what the AEffectiveness Monitoring Task Team@ is doing and play a role when possible.

 

5.      On projects such as Killarney Lake Timber Sale, an on-site visit by fisheries staff or perhaps improving training of other staff to ensure that standards are not overlooked.

 

6.      More effort needs to be put into working with private landowners in development of watershed improvement projects.

 

7.      There is an apparent need to adjust or eliminate grazing in Emerald Creek to meet RMO=s in INFISH.

 

8.      Recreation mining does not appear to be in compliance with INFISH and there is a need to minimize the impact of this activity.  There is a need for annual rehab of the area to accommodate the spring/winter runoff.

 

9.      Need a watershed assessment/analysis to determine how activities in Emerald Creek relate to each other in order to evaluate the cumulative effects and make recommendations to mitigate and restore the drainage.  Given the level of impacts and potential for development, the assessment may lead you to rationale for some hard trade-offs in order to meet INFISH/BO requirements and needs for species recovery and habitat restoration.

 

10.  Caution needs to be the exercised when proposing developments in RHCAs (i.e., Blue Creek boat ramp and/or recreation site). (Contributor, Fritz)

 

11.  Reestablish coordination with the state (particularly Fish and Game) and establish coordination with Tribes.

 

12.  Explore flexibility contained in INFISH, BO, and streamlining guidance to further tailor RHCAs to aquatic restoration needs and attainment of RMOs.

 

Feedback to Team

 

1.               Clarification of CERCLA/ESA guidance on what needs to be done - include fish hydrology.

 

2.               With new construction in RHCAs, is an EWAS required in all cases or only in priority watersheds.

 

3.               For ongoing projects that they know do not meet INFISH - what do they do?

Minimizing vs. Restoration

 

4.               Without fish present, do agencies need to consult, i.e., a definition of when agencies need to consult.

 

5.               When doing these reviews, integrate with other reviews.

 

6.               Cost for implementation of all that we are required to do is beyond our capability.  We need to balance what we are required to do with what we are financially capable of doing.

 

7.               Look at dates and stick with commitments in BOs.

 

8.               Report annual progress on INFISH/PACFISH BOs to Forest and District level staff.


 

Conclusions

 

Both the BLM and NF have an extremely high sensitivity to the requirements of INFISH and the BO.

 

Streamlining appears to be well established for consultation.

 

There is a close working relationship both between the NF and BLM and between the land management agencies and the USFWS.

 

Communication needs to be continually worked upon to ensure that standards are met.

 

The opportunities for completing priority restoration activities are severely limited by both the amount and method of providing funding.