Chapter 5 is a compilation of the management direction displayed in the description of the alternatives in Chapter 2 of this FEIS. The information is compiled in Chapter 5 to assist implementation teams in locating applicable management direction for site-specific projects. No new information is presented. When implementing site-specific projects based on the programmatic direction in this FEIS, it is recommended that implementation teams follow the process defined below:
Step 1 - Apply management direction in the appropriate Forest Plan.
When resource management activities occur in the locations shown in Table A - Limited Operating Periods, require the indicated limited operating periods. Regard limited operating periods as a standard mitigation, in lieu of site-specific survey information. Based on site-specific survey information, a Wildlife Biologist may modify the distance, duration, or need for a limited operating period
| SPECIES | LOCATION | LIMITED OPERATING PERIOD |
| Bald eagle | Within designated territories | November 1 through August 31 |
| Bald eagle | Winter roosts | November 1 through March 1 |
| Peregrine falcon | Within designated territories | February 1 through August 31 |
| California spotted owl | Within ¼ mile of a protected activity center boundary | March 1 through August 31 |
| Goshawk | Within ¼ mile of territory | March 1 through September 15 |
| Marten den | Within ½ mile of known sites | May 1 through August 1 |
| Fisher den | Within ½ mile of known sites | March 1 through July 1 |
| Wolverine den | Within ½ mile of known sites | February 1 through June 1 |
| Sierra Nevada red fox dens | Within ½ mile of known sites | February 1 through July 1 |
| Sandhill crane | Within ½ mile of nesting sites | April 1 through August 1 |
| Great gray owl | Within ½ mile of nesting sites | March 1 through August 31 |
| California red-legged frog | All unsurveyed and all occupied suitable habitat | October 1 through April 15 or after the first frontal system resulting in more than ¼ inch of precipitation, or both. If a dry period of 72 hours or more occurs after the onset of the rainy season, operations may resume. |
Management Direction for Noxious Weeds and Invasive
Exotic Plants
Using the following guidelines during site-specific planning and implementation,
manage National Forest System lands so that management activities do not
introduce or spread noxious or invasive exotic weeds:
Inventory: As part of site-specific planning, inventory project areas and adjacent areas (particularly access roads) for noxious and invasive exotic weeds.
Control: If noxious weeds are found in or adjacent to a site-specific project area, evaluate treatment options relative to the risk of weed spread without treatment. Evaluate control methods at the site-specific planning level.
Prevention/Cleaning: Require off-road equipment and vehicles (both Forest Service owned and contracted) used for project implementation to be weed-free. Clean equipment and vehicles of all attached mud, dirt, and plant parts. Use standard timber sale contract clause C6.343 – Cleaning of Equipment in timber sale contracts.
Prevention/Road Construction: Require all earth-moving equipment, gravel, fill, or other materials to be weed-free. Use onsite sand, gravel, rock, or organic matter, where possible. Evaluate road locations for weed risk factors.
Prevention/Revegetation: Use weed-free equipment, mulches, and seed sources. Avoid seeding in areas where revegetation will occur naturally, unless noxious weeds are a concern. Save topsoil from disturbance and put it back to use in onsite revegetation, unless contaminated with noxious weeds.
Prevention/Staging Areas: Do not stage equipment, materials, or crews in noxious weed infested areas where there is risk of spread to areas of low infestation.
Management Direction for Oaks
Where oak is present, retain an average 25 to 35 square feet basal
area per acre of oaks over 15 inches diameter at breast height (DBH). Site-specific
planning will determine feasibility and specific needs. Retain smaller
oaks, if determined to be necessary for future recruitment.
Management Direction for Riparian and Aquatic Areas
Prescribe minimum widths as "interim boundaries" as follows:
TM-2 and TM-3: Allow unscheduled timber harvest salvage operations only if Resource Management Objectives (RMO) are met or a prescription is needed to attain RMO.
Management Direction for Road Management
RF-4 - Require improvement of culverts and stream crossings
found to pose a substantial risk to riparian conditions to accommodate
at least a 100-year flood, including associated bedload and debris. Base
priorities for upgrading on the potential impact and ecological value of
the riparian resources affected. Design and construct new stream crossings
to accommodate at least a 100-year flood, including associated bedload
and debris.
RF-8 - Require a Road Management Plan be developed and carried out that meets the Resource Management Objectives (RMO).
Management Direction for Fire and Fuels
FM-1: Design fuel treatment to meet Resource Management Objectives
(RMO), and to minimize disturbance of riparian ground cover and vegetation.
FM-4: Design prescribed burn projects to protect Riparian Habitat Conservation Areas (RHCA) from burning. Where riparian ecosystems would be enhanced by prescribed burns, clearly identify the specific objectives and risks.
Management Direction for Watershed Restoration and
Habitat Protection
WR-1: A watershed analysis is a prerequisite to planning, implementing,
and monitoring all restoration projects.
WR-2: Conduct habitat assessments and surveys for California red-legged frogs in all areas below 5,500 feet in elevation. Within watersheds containing known populations, including French Creek Watershed and Chino Creek Watershed on the Plumas National Forest, implement a 300 foot buffer on all sides of waterways (including ephemeral wetlands). Within all identified California red-legged frog core areas, as identified in the California Red-Legged Frog Recovery Plan, involve the USDI Fish and Wildlife Service in early phases of site-specific project planning that implement resource management activities.