Table 23–Timber stand improvement program needs--fiscal years 1996-98

Table 23–Timber stand improvement program needs--fiscal years 1996-98      
  Current and Projected   Prior Year Projected 1/
  1,000 acres   1,000 acres
Fiscal year 1996    
10/1/95 balance 1,454   1,454
Actual needs 486   300
Actual accomplishments -260   -267
10/1/96 balance 1,680   1,487
Fiscal year 1997      
10/1/96 balance 1,680   1,487
New needs 350   300
Projected accomplishments -274   -207
10/1/97 balance 1,756   1,580
Fiscal year 1998:      
10/1/97 balance 1,756  
New needs 300    
Projected accomplishments -237    
Projected 10/1/98 balance 1,819 2/  
1/ Projections in FY 1995 Report of the Forest Service      
2/ This represents over 6 years of future projected accomplishments.      

Last Updated on 9/18/97