Go to main Deschutes National Forest web site

You are here: NEPA Home / Deschutes National Forest NEPA Projects / BPA-Pilot Butte-La Pine Line Pole Replacement

BPA-Pilot Butte-La Pine Line Pole Replacement

BPA proposes to replace 12 deteriorating wood pole structures along its Pilot Butte - La Pine 230 kV transmission line. The 12 replacements are located along a 25-mile section of the line within the BPA right of way and will be replaced in-kind.

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Additional construction or reconstruction of existing telephone or utility lines in a designated corridor.

Special Authority
Not applicable / Other

Lead Management Unit
Bend/Fort Rock Ranger District

Notice and Comment Regulation
215

Project Purpose
Special use management

Project Activity
Special use authorizations

Project Status

Current Status
Analysis Completed

Project Milestones

All planning milestones have been completed.

Project Decision Information

Bonneville Power Administration Pilot Butte to La Pine Pole Replacement Pro

Decision Signed Date
2012-07-16

Last Updated: 7/20/2012