19 Mile Brook Trail Temporary Reroute

Bridge destroyed by Tropical Storm Irene. Propose to install temporary step-stone crossing 500' upstream from bridge site and rock staircase to old road prism to link to trail. Cancelled because relocation upstream deemed unnecessary.

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Construction and reconstruction of trails.

Special Authority
Not applicable / Other

Lead Management Unit
Androscoggin Ranger District

Notice and Comment Regulation
215

Project Purpose
Recreation management

Project Activity
Trail management; Watershed improvements

Project Status

Current Status
Cancelled

Next Milestone: Notice of Initiation (est. 04/2012)

Last Updated: 6/08/2012