Westside Railroad Trail Reroute

Reroute a section of the Westside Railroad Trail that washed out in storm a event on March 20, 2011. The reroute would go upstream of the failure and be approximately 450 feet long.

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Construction and reconstruction of trails.

Special Authority
Not applicable / Other

Lead Management Unit
Mi-Wok Ranger District

Notice and Comment Regulation
Not Subject to Regulations

Project Purpose
Recreation management

Project Activity
Trail management

Project Status

Current Status
Analysis Completed

Project Milestones

All planning milestones have been completed.

Project Decision Information

Westside Railroad Trail Reroute

Decision Signed Date
2012-01-18

Last Updated: 1/26/2012