Midstate Whittier Power Line

Projects puropse is to supply power to Southern Deschutes County and to provide a more reliable power source for Midstate Electric Cooperative customers. 40 foot tall power poles would be installed every 300 feet along designated route.

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Approval, modification, or continuation of minor, short-term (one year or less) special uses of National Forest System lands.

Special Authority
Not applicable / Other

Lead Management Unit
Bend/Fort Rock Ranger District

Notice and Comment Regulation
215

Project Purpose
Special use management

Project Activity
Special use authorizations

Project Status

Current Status
Analysis Completed

Project Milestones

All planning milestones have been completed.

Project Decision Information

Midstate Electric - Whittier Overhead Powerline Project Decision Memo

Decision Signed Date
2012-06-05