Projects puropse is to supply power to Southern Deschutes County and to provide a more reliable power source for Midstate Electric Cooperative customers. 40 foot tall power poles would be installed every 300 feet along designated route.
Project Information
Expected Analysis Type
Decision Memo
Categorical Exclusion
Approval, modification, or continuation of minor, short-term (one year or less) special uses of National Forest System lands.
Special Authority
Not applicable / Other
Lead Management Unit
Bend/Fort Rock Ranger District
Notice and Comment Regulation
215
Project Purpose
Special use management
Project Activity
Special use authorizations
Project Status
Current Status
Analysis Completed
Project Milestones
All planning milestones have been completed.
Project Decision Information
Midstate Electric - Whittier Overhead Powerline Project Decision Memo
Decision Signed Date
2012-06-05