Metolius River Trails Improvement Project

The project will restore about 61 trail sites and replace bridges along the Metolius River. Sites adjacent to the river are bleeding sediment and affecting fish habitat. The log bridges are old and need to be replaced to protect public safety.

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Construction and reconstruction of trails.

Special Authority
Not applicable / Other

Lead Management Unit
Sisters Ranger District

Notice and Comment Regulation
215

Project Purpose
Recreation management

Project Activity
Trail management

Project Status

Current Status
Analysis Completed

Project Milestones

All planning milestones have been completed.

Project Decision Information

Metolius River Trail Restoration Project

Decision Signed Date
2012-05-30

Last Updated: 6/25/2012