Fish Passage Improvements on Soda and Goose Creeks

The culvert at Goose Cr. will be replaced with a larger diameter culvert pipe; at Soda Cr. with a bridge or pre-facbricated box culvert. Bankfull channel widths would be exceeded at both sites, improving the passage of large wood and debris.

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Modification or maintenance of stream or lake aquatic habitat improvement structures using native materials or normal practices.

Special Authority
Not applicable / Other

Lead Management Unit
Bend/Fort Rock Ranger District

Notice and Comment Regulation
Not Subject to Regulations

Project Purpose
Wildlife, Fish, Rare plants; Watershed management

Project Activity
Species habitat improvements; Road improvements/construction; Watershed improvements

Project Status

Current Status
Analysis Completed

Project Milestones

All planning milestones have been completed.

Project Decision Information

Soda and Goose Creek Fish Passage Improement Project

Decision Signed Date
2011-10-03