Portland General Electric proposes to construct, maintain, and operate a 500 kV, single-circuit transmission line that would cross 1.2 miles of the Mt. Hood National Forest.
Project Information
Expected Analysis Type
Environmental Impact Statement
Special Authority
Not applicable / Other
Lead Management Unit
Mt. Hood National Forest All Units
Notice and Comment Regulation
215
Project Purpose
Special use management
Project Activity
Electric Transmission
Project Status
Current Status
Under Analysis
Last Completed Milestone: Notice of Initiation (06/01/2010)
Next Milestone: Comment Period (est. 10/2013)
Last Updated: 3/22/2013