Lake Ouachita Vista Trail, High Water Spur

Approximately 1/4 mile trail construction as alternative route where the lake is high

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Construction and reconstruction of trails.

Special Authority
Not applicable / Other

Lead Management Unit
Womble Ranger District

Notice and Comment Regulation
Not Subject to Regulations

Project Purpose
Recreation management

Project Activity
Trail management

Project Status

Current Status
Analysis Completed

Project Milestones

All planning milestones have been completed.

Project Decision Information

Lake Ouachita Vista High Water Spur

Decision Signed Date
2010-07-06