East Fork Encampment Weir Removal

Remove hydrology weir constructed by the USFS in 1960s that is preventing fish movement upstream and restore approximately 800' of stream channel. Removal of weir will provide access to eight miles of stream.

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Modification or maintenance of stream or lake aquatic habitat improvement structures using native materials or normal practices.

Special Authority
Not applicable / Other

Lead Management Unit
Brush Creek/Hayden Ranger District

Notice and Comment Regulation
Not Subject to Regulations

Project Purpose
Wildlife, Fish, Rare plants

Project Activity
Species habitat improvements; Species population enhancements

Project Status

Current Status
Analysis Completed

Project Milestones

All planning milestones have been completed.

Project Decision Information

East Fork Encampment River Weir Removal Project

Decision Signed Date
2011-05-13

Last Updated: 6/28/2011