Project proposes to use a combination of commercial & non-commercial harvest, mowing, and underburning to restore and maintain fire dependent ecosystems & to maintain forest health. Project proposes to treat approximately 10,875 acres.
Project Information
Expected Analysis Type
Environmental Impact Statement
Special Authority
Not applicable / Other
Lead Management Unit
Bend/Fort Rock Ranger District
Notice and Comment Regulation
215
Project Purpose
Fuels management; Vegetation management (other than forest products)
Project Activity
Road decommissioning; Fuel treatments (non-activity fuels); Forest vegetation improvements; Plan amendment; Timber sales (green)
Project Status
Current Status
Analysis Completed
Project Milestones
All planning milestones have been completed.
Project Decision Information
Deadlog Vegetation Management Project
Decision Signed Date
2009-10-25