precommercial thinning, pruning and brush mastication on approximately 700acres of conifer tree plantations and creation of a shaded fuel break along rainbow ridge for approximately 1.0 miles
Project Information
Expected Analysis Type
Decision Memo
Categorical Exclusion
Timber stand and/or wildlife habitat improvement activities which do not include the use of herbicides or do not require more than one mile of low standard road construction (Service Level D, FSH 7709.56)
Special Authority
Not applicable / Other
Lead Management Unit
Mt. Shasta Ranger District
Notice and Comment Regulation
215
Project Purpose
Vegetation management (other than forest products)
Project Activity
Forest vegetation improvements
Project Status
Current Status
Analysis Completed
Project Milestones
All planning milestones have been completed.
Project Decision Information
Deer Creek TSI & Rainbow Ridge Fuelbreak Continuation Project
Decision Signed Date
2011-06-13
Last Updated: 6/16/2011