SOUTHERN CALIFORNIA EDISION REPLACEMENT OF 19 DETERIORATED WOOD POLES

Proposal for replacement of 19 deteriorated wood poles with light weight steel poles on the Borel-Isabella-KR3-Lakegen-Weldon and Borel-Havilah-Loraine-Monolith-Walker Basin 66kV transmission lines, Lower and Upper Kern River Canyon

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Additional construction or reconstruction of existing telephone or utility lines in a designated corridor.

Special Authority
Not applicable / Other

Lead Management Unit
Kern River Ranger District

Notice and Comment Regulation
215

Project Purpose
Special use management

Project Activity
Special use authorizations

Project Status

Current Status
Analysis Completed

Project Milestones

All planning milestones have been completed.

Project Decision Information

SCE Replmt of 19 Deteriorated Wood Poles with Light Weight Steel Poles DM

Decision Signed Date
2012-11-30

Last Updated: 12/27/2012