Proposal for replacement of 19 deteriorated wood poles with light weight steel poles on the Borel-Isabella-KR3-Lakegen-Weldon and Borel-Havilah-Loraine-Monolith-Walker Basin 66kV transmission lines, Lower and Upper Kern River Canyon
Project Information
Expected Analysis Type
Decision Memo
Categorical Exclusion
Additional construction or reconstruction of existing telephone or utility lines in a designated corridor.
Special Authority
Not applicable / Other
Lead Management Unit
Kern River Ranger District
Notice and Comment Regulation
215
Project Purpose
Special use management
Project Activity
Special use authorizations
Project Status
Current Status
Analysis Completed
Project Milestones
All planning milestones have been completed.
Project Decision Information
SCE Replmt of 19 Deteriorated Wood Poles with Light Weight Steel Poles DM
Decision Signed Date
2012-11-30
Last Updated: 12/27/2012