Campground Concessionaire Special Use Permit

Administrative action to reissue campground concessionaire permit for 23 WMNF campgrounds and day use sites beginning January 2013 because term on existing permit expires. Decision withdrawn due to national court ruling on CEs to allow 30-day comment

Project Information

Expected Analysis Type
Decision Memo

Categorical Exclusion
Issuance of a new special use authorization for a new term to replace an existing or expired special use authorization when the only changes are administrative, there are no changes to the authorized facilities or increases in the scope or intensity of authorized activities, and the applicant or holder is in full compliance with the terms and conditions of the special use authorization.

Special Authority
Not applicable / Other

Lead Management Unit
White Mountain National Forest All Units

Notice and Comment Regulation
215

Project Purpose
Special use management; Recreation management

Project Activity
Developed site management; Special use authorizations

Project Status

Current Status
Analysis Completed

Project Milestones

All planning milestones have been completed.

Project Decision Information

Campground Concessionaire Special Use Permit Decision Memo

Decision Signed Date
2012-03-20

Campground Concessionaire Special Use Permit Decisionmemo

Decision Signed Date
2012-05-21