Rio Grande Corridor at Buckman Restoration and Recreation Enhancement Project

Remove non-native vegetation with selective use of herbicide and plant native trees/shrubs along the Rio Grande at Buckman site. Development of a parking area, restroom and shade structures on NFS land. Parking/trailhead development on BLM land.

Project Information

Expected Analysis Type
Environmental Assessment

Special Authority
Not applicable / Other

Lead Management Unit
Espanola Ranger District

Notice and Comment Regulation
215

Project Purpose
Recreation management

Project Activity
Developed site management; Facility improvements/construction; Dispersed recreation mgmt.

Project Status

Current Status
Analysis Completed

Project Milestones

All planning milestones have been completed.

Project Decision Information

Rio Grande Corridor at Buckman Restoration and Recreation Enhancement Prj.

Decision Signed Date
2012-11-15

Last Updated: 11/20/2012