Darby Canyon Trailhead Relocation

Relocate trailhead .25 miles west to a location away from Darby Creek to protect water quality, fisheries and reduce trailhead congestion. Rehabilitate the road beyond new trailhead and convert to a nonmotorized trail. Replace main trail bridge.

Project Information

Expected Analysis Type
Environmental Assessment

Special Authority
Not applicable / Other

Lead Management Unit
Teton Basin Ranger District

Notice and Comment Regulation
215

Project Purpose
Wildlife, Fish, Rare plants; Recreation management

Project Activity
Road decommissioning; Developed site management

Project Status

Current Status
Under Analysis

Last Completed Milestone: Comment Period (12/13/2012)

Next Milestone: NEPA or Forest Plan Amendment Decision Document Available (est. 01/2013)

Last Updated: 12/17/2012