FSH 2709.15 - HYDROELECTRIC HANDBOOK 2/87 WO 24.1-Exhibit 1 TIMELINE COMPARISON OF LICENSES AND EXEMPTIONS FOR PROJECTS NOT REQUIRING AS EIS COMMON TIMELINE AFPP FERC Notice FS Response (critical items) STAGE I Application for Investigation SUP FS Scoping (issues, pub. invol. needs, study needs, alts.) Investigation SUP Issued STAGE II Feasibility, Studies, Scoping, Public Invol., Alternatives, Consultation, Conceptual design SEPARATE TIMELINE COMPARISIONS APPLICATION FOR LICENSE APPLICATION FOR EXEMPTION ***STAGE II CONTINUED*** Draft AFL / AFSUA Draft AFE / AFSUA Detailed FS IDT Review Brief of Detailed IDT Review Response to Applicant Response to Applicant ***STAGE III*** AFL / AFSUA AFE / AFSUA Notice Notice Formal FS IDT Analysis FS IDT Analysis for Recommendation 4(e) Preparation to FERC Comments FS Response to FERC on Critical EA / DN / FONSI items (unless CE) Consistency Recommendation / FS May Defer Detailed Review SUA Decision Until SUA Process License Conditions ***POST STAGE III*** FERC Analysis of information FERC EA With FS Input completed FERC License Decision(w/EA etc.) FERC Exemption Decision FS ACTION FS ACTION No Decision (already made) Use FERC EA Issue SUA Use AFSUA Do or Finalize analysis Verify Documentation Issue EA, DN, FONSI Issue SUA CONSTRUCTION CONSTRUCTION KEY OF TERMS IN TIMELINE COMPARISON CHART AFPP - application for preliminary permit FERC - Federal Energy Regulatory Commission FS - Forest Service SUP - special-use permit pub. invol. - public involvement alts. - alternatives AFL - application for license AFE - application for exemption AFSUA - application for special-use authorization IDT - interdisciplinary team EA - environmental assessment DN - decision notice FONSI - finding of no significant impact CE - categorical exclusion SUA - special-use authorization