Timeline and Process

Clearwater and Nez Perce
Forest Plan Revision Timeline
Under the 2005 Planning Rule

May 19, 2005

Notice of Adjustment stating the zone’s intent to revise using the 2005 rule was published in the Federal Register

May 25, 2005

A one-page handout regarding the 2005 rule was mailed to individuals on the forest plan revision mailing list.

May 2005 – Late Winter/ Early Spring 2007

Use public comments and information and ideas collected from ongoing collaboration to develop proposed forest plans. Resolve national issues regarding a consistent approach to developing forest plans.

Spring 2007

Release proposed forest plans

90-day comment period

Use public comments to develop forest plan

Release forest plans; initiate 30-day objection period

Attempt to resolve objections

2008

Unresolved objections will be considered by a reviewing official who will decide the outcome and issue instructions to the forests. Forests will adjust the plans and issue final plans and plan approval documents.




USDA Forest Service - Clearwater Nez Perce Forest Plan Revision